On june 15, 2018, sanderson construction entered into a long-term construction contract to build a baseball stadium in washington, d. c., for $410 million. the expected completion date is april 1, 2020, just in time for the 2020 baseball season. costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):
2018 2019 2020
cost incurred during the year $90 $60 $80
estimated costs to complete as of dec 31 150 50 -
required:
1. compute the revenue and gross profit will sanderson report in its 2018, 2019, and 2020 income statements related to this contract assuming sanderson recognizes revenue over time according to percentage of completion.
2. compute the revenue and gross profit will sanderson report in its 2018, 2019, and 2020 income statements related to this contract assuming this project does not qualify for revenue recognition over time.
3. suppose the estimated costs to complete at the end of 2019 are $150 million instead of $50 million. compute the amount of revenue and gross profit or loss to be recognized in 2019 using the percentage of completion method.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 11:00
Alocal barnes and noble bookstore ordered 80 marketing books but received 60 books. what percent of the order was missing?
Answers: 1
question
Business, 22.06.2019 22:30
Ski powder resort ends its fiscal year on april 30. the business adjusts its accounts monthly, but closes them only at year-end (april 30). the resort's busy season is from december 1 through march 31. adrian pride, the resort's chief financial officer, the museums a close watch on lift ticket revenue and cash. the balances of these accounts at the end of each of the last five months are as follows:
Answers: 3
question
Business, 23.06.2019 00:30
Anational survey asked people, "how often do you eat out for dinner, instead of at home? " the frequencies were as follows.
Answers: 2
question
Business, 23.06.2019 02:20
Speedy auto repairs uses a job-order costing system. the company’s direct materials consist of replacement parts installed in customer vehicles, and its direct labor consists of the mechanics’ hourly wages. speedy’s overhead costs include various items, such as the shop manager’s salary, depreciation of equipment, utilities, insurance, and magazine subscriptions and refreshments for the waiting room. the company applies all of its overhead costs to jobs based on direct labor-hours. at the beginning of the year, it made the following estimates: direct labor-hours required to support estimated output 20,000 fixed overhead cost $ 350,000 variable overhead cost per direct labor-hour $ 1.00 required: 1. compute the predetermined overhead rate. 2. during the year, mr. wilkes brought in his vehicle to replace his brakes, spark plugs, and tires. the following information was available with respect to his job: direct materials $ 590 direct labor cost $ 109 direct labor-hours used 6
Answers: 1
You know the right answer?
On june 15, 2018, sanderson construction entered into a long-term construction contract to build a b...
Questions
question
Mathematics, 06.05.2021 03:20
question
History, 06.05.2021 03:20
question
Mathematics, 06.05.2021 03:20
question
English, 06.05.2021 03:20
question
Social Studies, 06.05.2021 03:20
Questions on the website: 13722362