Consider the following work breakdown structure:
time estimates (days)
activity precedes optimistic most likely pessimistic
start a, b, c - - -
a d 38 50 62
b e 90 99 108
c end 85 100 115
d f 19 25 31
e end 91 100 115
f end 62 65 68
what is the estimated expected (mean) time for project completion?

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 09:50
phillips, inc. had the following financial data for the year ended december 31, 2019. cash $ 41,000 cash equivalents 75,000 long term investments 59,000 total current liabilities 149,000 what is the cash ratio as of december 31, 2019, for phillips, inc.? (round your answer to two decimal places.)
Answers: 3
question
Business, 22.06.2019 12:40
When cell phones were first entering the market, they were relatively large and reception was undependable. all cell phones were essentially the same. but as the technology developed, many competitors entered, introducing features unique to their phones. today, cell phones are only a small fraction of the size and weight of their predecessors. consumers can buy cell phones with color screens, cameras, internet access, daily planners, or voice activation (and any combination of these features). the history of the cell phone demonstrates what marketing trend?
Answers: 3
question
Business, 22.06.2019 14:20
Anew 2-lane road is needed in a part of town that is growing. at some point the road will need 4 lanes to handle the anticipated traffic. if the city's optimistic estimate of growth is used, the expansion will be needed in 4 years and has a probability of happening of 40%. for the most likely and pessimistic estimates, the expansion will be needed in 8 and 15 years respectively. the probability of the pessimistic estimate happening is 20%. the expansion will cost $ 4.2 million and the interest rate is 8%. what is the expected pw the expansion will cost?
Answers: 1
question
Business, 22.06.2019 16:20
There are three factors that can affect the shape of the treasury yield curve (r* t , ip t , and mrp t ) and five factors that can affect the shape of the corporate yield curve (r* t , ip t , mrp t , drp t , and lp t ). the yield curve reflects the aggregation of the impacts from these factors. suppose the real risk-free rate and inflation rate are expected to remain at their current levels throughout the foreseeable future. consider all factors that affect the yield curve. then identify which of the following shapes that the us treasury yield curve can take. check all that apply.a. downward-sloping yield curveb. upward-sloping yield curvec. inverted yield curve
Answers: 1
You know the right answer?
Consider the following work breakdown structure:
time estimates (days)
activity prece...
Questions
question
History, 23.03.2020 22:35
question
English, 23.03.2020 22:35
Questions on the website: 13722361