Suppose you have a project with four tasks as follows: task 1 can start immediately and has a duration of 2. task 2 can start after task 1 is completed and has an estimated duration of 4. task 3 can start after task 2 has been completed and has an estimated duration of 5. task 4 can start after task 1 is completed and must be completed when task 3 is completed. its estimated duration is 8. what is the length of the critical path for this project? 9 10 11 12

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 21:00
Resources and capabilities, such as interpersonal relations among managers and a firm's culture, that may be costly to imitate because they are beyond the ability of firms to systematically manage and influence are referred to asanswers: socially complex.causally ambiguous.path dependent.the result of unique historical conditions.
Answers: 3
question
Business, 22.06.2019 08:30
The production manager of rordan corporation has submitted the following quarterly production forecast for the upcoming fiscal year: 1st quarter 2nd quarter 3rd quarter 4th quarter units to be produced 10,800 8,500 7,100 11,200 each unit requires 0.25 direct labor-hours, and direct laborers are paid $20.00 per hour. required: 1. prepare the company’s direct labor budget for the upcoming fiscal year. assume that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced. 2. prepare the company’s direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is not adjusted each quarter. instead, assume that the company’s direct labor workforce consists of permanent employees who are guaranteed to be paid for at least 2,500 hours of work each quarter. if the number of required direct labor-hours is less than this number, the workers are paid for 2,500 hours anyway. any hours worked in excess of 2,500 hours in a quarter are paid at the rate of 1.5 times the normal hourly rate for direct labor.
Answers: 2
question
Business, 22.06.2019 08:40
Which of the following is not a characteristic of enterprise applications that cause challenges in implementation? a. they introduce "switching costs," making the firm dependent on the vendor. b. they cause integration difficulties as every vendor uses different data and processes. c. they are complex and time consuming to implement. d. they support "best practices" for each business process and function. e. they require sweeping changes to business processes to work with the software.
Answers: 1
question
Business, 22.06.2019 16:40
An electronics store is running a promotion where for every video game purchased, the customer receives a coupon upon checkout to purchase a second game at a 50% discount. the coupons expire in one year. the store normally recognized a gross profit margin of 40% of the selling price on video games. how would the store account for a purchase using the discount coupon?
Answers: 3
You know the right answer?
Suppose you have a project with four tasks as follows: task 1 can start immediately and has a durat...
Questions
Questions on the website: 13722360