In using the net present value method, only projects with a zero or positive net present value are acceptable because:
a. the return from these projects equals or exceeds the cost of capital
b. a positive net present value on a particular project guarantees company profitability
c. the company will be able to pay the necessary payments on any loans secured to finance the project
d. both a and b are correc

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 03:30
In return for their with optimizing his painting project, the castle servant informed poly and digit that he saw someone dressed as the king leaving behind a trail of crumbs as he walked into the jester's room late last night. poly and digit have finally found the crisp-collecting culprit — it turns out the jester's shoe size and hair color match the clues that were found! in gratitude, poly and digit agree to the servant with his current task of replacing all of the tables and chairs in the castle. his goal is to determine which furniture company should produce the new furniture. he receives information from a company that customizes elegant furniture, and he wants to analyze the company's production process in order to calculate some problems about cost and availability. read the following scenario, and assist poly and digit as they the servant with his calculations. the fit for a king furniture company requires 2020 hours of labor to produce a standard table, and a chair requires 1212 hours of labor. the labor available is 565565 hours per week. the company can produce at most 3535 chairs per week.
Answers: 1
question
Business, 22.06.2019 20:00
After testing its water, a city water department issues a report to the related citizens, noting what chemicals have been identified, their doses, and the estimated risks of exposure at these levels. this report represents a type of
Answers: 1
question
Business, 22.06.2019 22:40
Effective capacity is the: a. capacity a firm expects to achieve given the current operating constraints.b. minimum usable capacity of a particular facility.c. sum of all the organization's inputs.d. average output that can be achieved under ideal conditions.e. maximum output of a system in a given period.
Answers: 1
question
Business, 23.06.2019 00:00
Review the key ethical and social issues over the last five decades and place each on the timeline in chronological order. note that once you complete this part of the question, you will be unable to adjust your answers.
Answers: 3
You know the right answer?
In using the net present value method, only projects with a zero or positive net present value are a...
Questions
question
Mathematics, 17.04.2020 20:43
question
Mathematics, 17.04.2020 20:43
question
Mathematics, 17.04.2020 20:43
question
Mathematics, 17.04.2020 20:43
Questions on the website: 13722362