A12-station automated production line has an ideal cycle time of 30 sec. line stops occur on average once every 20 cycles. when a line stop occurs, average downtime is 4.0 min. cost of each starting work part is $1.55, and the cost to operate the line is $66/hr. tooling cost is $0.27 per work part. determine (a) average hourly production rate, (b) line efficiency, and (c) cost of a workpiece produced.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 10:20
What two things do you consider when evaluating the time value of money
Answers: 1
question
Business, 22.06.2019 12:10
Drag each label to the correct location on the image determine which actions by a manager are critical interactions - listening to complaints - interacting with customers - responding to complaints - assigning staff duties -taking action to address customer grievances -keeping track of reservations
Answers: 2
question
Business, 22.06.2019 12:40
Evan company reports net income of $232,000 each year and declares an annual cash dividend of $100,000. the company holds net assets of $2,130,000 on january 1, 2017. on that date, shalina purchases 40 percent of evan's outstanding common stock for $1,066,000, which gives it the ability to significantly influence evan. at the purchase date, the excess of shalina’s cost over its proportionate share of evan’s book value was assigned to goodwill. on december 31, 2019, what is the investment in evan company balance (equity method) in shalina’s financial records?
Answers: 2
question
Business, 22.06.2019 19:00
Describe how to write a main idea expressed as a bottom-line statement
Answers: 3
You know the right answer?
A12-station automated production line has an ideal cycle time of 30 sec. line stops occur on average...
Questions
question
Chemistry, 22.08.2019 15:10
Questions on the website: 13722367