You have recently joined an organization that is just beginning to follow formal project management practices. in a meeting, your manager describes your next assignment, a project to select and implement a new telephone system for the customer service department. when you request a signed charter authorizing you to begin work, the manager suggests you "just draft something." which of the following is true about the development of a project charter?
a. the sponsor creates the project charter, and the project manager approves it.
b. the project team creates the project charter, and the pmo approves it.
c. the executive manager creates the project charter, and the functional manager approves it.
d. the project manager creates the project charter, and the sponsor approves it.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 00:40
Gdonald was unhappy that his company did not provide good transport facilities. he found it very strenuous to drive to work on his own, and this eventually led to job dissatisfaction. hence, he recommended ways to solve this problem. according to the evln model, this information suggests that donald's main reaction to job dissatisfaction was:
Answers: 3
question
Business, 22.06.2019 23:20
You work as the sales manager for a company that sells office supplies to businesses of all sizes. because the profit margins are razor-thin, you need to ensure that you are getting the very best prices on paper, pencils, pens, post-it notes, and other office supplies from the manufacturers. when reviewing the quarterly profit statement, you realize that your costs are higher than they should be, and you trace the higher costs back to an employee who has been lax about getting competitive bids to ensure the lowest prices. when you conduct your research to determine the reason for the higher costs, and take action to bring those costs back down, in which of the key management processes are you taking part?
Answers: 3
question
Business, 23.06.2019 02:20
You park your car on sixth street and walk over to the quad for lunch. while crossing wright street, you are hit by a bicyclist and knocked to the ground. you hit your head so hard you are knocked out. when you wake up, the person who hit you is gone. you incur $45,000 in medical bills. the person who hit you would be liable for $150,000 in damages if you could find them. your policy will pay:
Answers: 1
question
Business, 23.06.2019 03:00
What are the uses of national income data
Answers: 1
You know the right answer?
You have recently joined an organization that is just beginning to follow formal project management...
Questions
question
Mathematics, 27.06.2019 16:30
question
Mathematics, 27.06.2019 16:30
question
Mathematics, 27.06.2019 16:30
question
Mathematics, 27.06.2019 16:30
Questions on the website: 13722363