Erie company manufactures a mobile fitness device called the jogging mate. the company uses standards to control its costs. the labor standards that have been set for one jogging mate are as follows:

standard
hours standard rate
per hour standard
cost
18 minutes $17.00 $5.10
during august, 5,750 hours of direct labor time were needed to make 20,000 units of the jogging mate. the direct labor cost totaled $102,350 for the month.

required:

1. what is the standard labor-hours allowed (sh) to makes 20,000 jogging mates?

2. what is the standard labor cost allowed (sh × sr) to make 20,000 jogging mates?

3. what is the labor spending variance?

4. what is the labor rate variance and the labor efficiency variance?

5. the budgeted variable manufacturing overhead rate is $4 per direct labor-hour. during august, the company incurred $21,850 in variable manufacturing overhead cost. compute the variable overhead rate and efficiency variances for the month.

(for requirements 3 through 5, indicate the effect of each variance by selecting "f" for favorable, "u" for unfavorable, and "none" for no effect (i. e., zero variance). input all amounts as positive values. do not round intermediate calculations.)

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 10:30
Issued to the joint planning and execution community (jpec) initiates the development of coas; it also requests that the supported ccdr submit a commander's estimate of the situation with a recommended coa to resolve the situation (joint force command and staff participation in the joint operation planning and execution system, page 10)
Answers: 2
question
Business, 22.06.2019 11:40
Select the correct answer. which is a benefit of planning for your future career? a.being less prepared after high school. b.having higher tuition in college. c.earning college credits in high school. d.ruining your chances of having a successful career.
Answers: 2
question
Business, 22.06.2019 15:10
Paddock pools constructed a swimming pool and deck for the jensens' home. paddock installed the wrong trim on the pool. it would cost $2800 to change the trim-one-fifth of the total cost of the pool. the jensens refuse to pay anything for the pool. the paddock's best defense is: (a) duress (b) substanial performance (c)mistake (d) failure of conditions
Answers: 3
question
Business, 22.06.2019 15:30
For a firm that uses the weighted average method of process costing, which of the following must be true? (a) physical units can be greater than or less than equivalent units. (b) physical units must be equal to equivalent units. (c) equivalent units must be greater than or equal to physical units. (d) physical units must be greater than or equal to equivalent units.
Answers: 1
You know the right answer?
Erie company manufactures a mobile fitness device called the jogging mate. the company uses standard...
Questions
question
Mathematics, 30.06.2019 23:30
question
Mathematics, 30.06.2019 23:30
question
Mathematics, 30.06.2019 23:30
Questions on the website: 13722361