When it is necessary to reduce project duration and resources are constrained, which of the following is not a reasonable option?
select one:
a. compromise quality
b. establishing a core project team
c. reduce project scope
d. fast-tracking
e. critical-chain project management

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 18:30
> > objectives define federalism and explain why the framers adopted a federal system instead of a unitary system. categorize powers delegated to and denied to the national government, and powers reserved for and denied to the states, and the difference between exclusive and concurrent powers.
Answers: 1
question
Business, 22.06.2019 20:50
Barbara flynn is in charge of maintaining hospital supplies at general hospital. during the past year, the mean lead time demand for bandage bx-5 was 65 (and was normally distributed). furthermore, the standard deviation for bx-5 was 6. ms. flynn would like to maintain a 90% service level.refer to the standard normal table for z-values.a) what safety stock level do you recommend for bx-5? safety stock=)what is the appropriate reorder point? reorder point=
Answers: 1
question
Business, 23.06.2019 02:00
Acompany sells garden hoses and uses the perpetual inventory system to account for its merchandise. the beginning balance of the inventory and its transactions during september were as follows:
Answers: 2
question
Business, 23.06.2019 10:00
When the amount paid for land is $36,000 and the amount paid for expenses is $10,000, the balance in total assets after transaction (b) is
Answers: 1
You know the right answer?
When it is necessary to reduce project duration and resources are constrained, which of the followin...
Questions
Questions on the website: 13722363