Activity 7-8 is directly preceded by two activitiesactivity 5-7 and activity 6-7. activity 5-7 has an expected time of five and an es time of six. activity 6-7 has an expected time of seven and an es time of seven. activity 7-8 has an expected time of 10. the es for activity 7-8 is: a) 11b) 14c) 21d) 24e) 25

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 11:20
Camilo is a self-employed roofer. he reported a profit of $30,000 on his schedule c. he had other taxable income of $5,000. he paid $3,000 for hospitalization insurance. his self-employment tax was $4,656. he paid his former wife $4,000 in court-ordered alimony and $4,000 in child support. what is the amount camilo can deduct in arriving at adjusted gross income (agi)?
Answers: 2
question
Business, 22.06.2019 17:00
Can someone me ? i’ll mark the best answer brainliest : )
Answers: 1
question
Business, 22.06.2019 17:30
Communication comes in various forms. which of the following is considered an old form of communication? a) e-mail b) letter c) skype d) texting
Answers: 2
question
Business, 22.06.2019 21:50
Which three of the following expenses can student aid recover? -tuition -television -school supplies -parties and socializing -boarding/housing
Answers: 2
You know the right answer?
Activity 7-8 is directly preceded by two activitiesactivity 5-7 and activity 6-7. activity 5-7 has a...
Questions
question
Mathematics, 19.03.2021 19:30
question
Mathematics, 19.03.2021 19:30
question
Mathematics, 19.03.2021 19:30
Questions on the website: 13722359