Business, 30.11.2019 00:31 kalebstone8357

Your project to obtain charitable donations is now 41 days into a planned 51-day project. the project is divided into 3 activities. the first activity is designed to solicit individual donations. it is scheduled to run the first 34 days of the project and to bring in $25,700. even though we are 41 days into the project, we still see that we have only 90% of this activity complete. the second activity relates to company donations and is scheduled to run for 41 days starting on day 7 and extending through day 48. we estimate that even though we should have (34/41) 83% of this activity complete, it is actually only 54% complete. this part of the project was scheduled to bring in $150,700 in donations. the final activity is for matching funds. this activity is scheduled to run the last 10 days of the project and has not started. it is scheduled to bring in an additional $51,400. so far $178,000 has actually been brought in on the project. calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index. (negative values should be indicated by a minus sign. do not round intermediate calculations. round your dollar amounts to the nearest whole number. round your "performance index" values to 3 decimal places.)

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 20:10
With signals from no-claim bonuses and deductibles, a. the marginal cost curve for careful drivers lies to the left of the marginal cost curve for aggressive drivers b. auto insurance companies insure more aggressive drivers than careful drivers because aggressive drivers have a greater need for the insurance c. the market for car insurance has a separating equilibrium, and the market is efficient d. most drivers pay higher premiums than if the market had no signals
Answers: 1
question
Business, 22.06.2019 23:40
Gdp has grown in a country at 3% per year for the last 20 years. the labor force has grown at 2% per year and the quantity of physical capital has grown at 4% per year. a 1% increase in average physical capital per worker (other things equal) raises productivity by 0.3%. average education has not changed. how much has growing physical capital per worker contributed to productivity growth in this country? choose the correct answer from the following choices, and then select the submit answer button. answer choices 0.3% 0.6% 3.0% 6.0%
Answers: 1
question
Business, 23.06.2019 03:30
What does the term "smalling up" mean, according to white? what ways have you or people you know had to "small up"? if you haven't, what ways could you?
Answers: 2
question
Business, 23.06.2019 17:30
Financial markets and channel to . they also channel money from individuals who want to for the future to those who need cash to spend today. a third function of financial markets is to allow individuals and businesses to adjust their risk. for example, , such as the vanguard index fund, and , such as spdr's or “spiders,” allow individuals to spread their risk across a large number of stocks. financial markets provide other mechanisms for sharing risks. for example, a wheat farmer and a baker may use the to reduce their exposure to wheat prices. financial markets and intermediaries allow investors to turn an investment into cash when needed. for example, the of public companies are because they are traded in huge volumes on the . are the main providers of payment services by offering checking accounts and electronic transfers. finally, financial markets provide information. for example, the of a company that is contemplating an issue of debt can look at the yields on existing to gauge how much interest the company will need to pay.
Answers: 3
You know the right answer?
Your project to obtain charitable donations is now 41 days into a planned 51-day project. the projec...