You manage a project with 10 activities. activities a1, a3, a5, a9 form the critical path. as you have a large budget for the project, you are considering crashing activity a2, which has the potential to shorten the time of a2 by 3 days.
what do you think about this opportunity?
o a good idea, it will reduce the project duration by 3 days.
o a bad idea, as a2 is not on the critical path.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 19:30
Why does the united states government provide tax breaks related to the amount of money companies spend on research and development? a. to provide incentives for companies to conduct research and development to allow antitrust authorities b. to challenge joint research efforts c. to protect the right of inventors d. to produce and sell their inventions e. to involve less government scrutiny than a government funded project
Answers: 1
question
Business, 21.06.2019 19:30
How does knowing about supply and demand
Answers: 1
question
Business, 22.06.2019 18:30
Amanufacturer has paid an engineering firm $200,000 to design a new plant, and it will cost another $2 million to build the plant. in the meantime, however, the manufacturer has learned of a foreign company that offers to build an equivalent plant for $2,100,000. what should the manufacturer do?
Answers: 1
question
Business, 23.06.2019 00:30
You have been solicited to conduct a performance evaluation for a public organization that has been corrupted over issues of personnel embezzling funds. before actually conducting the evaluation, you—the evaluator—need to know certain specifics to conduct a thorough evaluation. compose a proposal that describes what type of evaluation will be conducted. in the proposal, explain the type of public organization. describe some of the main services, products, and activities the organization provides to the public. describe the size of the problem, who is affected by the problem, how long the problem has been in existence, and how long the evaluation will take. also, describe what the evaluation will assess with respect to organizational leadership. finally, what outcomes do you propose the evaluation will to achieve for the organization?
Answers: 2
You know the right answer?
You manage a project with 10 activities. activities a1, a3, a5, a9 form the critical path. as you ha...
Questions
question
English, 29.03.2021 14:00
question
English, 29.03.2021 14:00
question
English, 29.03.2021 14:00
question
Engineering, 29.03.2021 14:00
Questions on the website: 13722367