The flapjack corporation had 8,200 actual direct labor hours at an actual rate of $12.40 per hour. original

production had been budgeted for 1,100 units, but only 1,000 units were actually produced. labor

standards were 7.6 hours per completed unit at a standard rate of $13.00 per hour.

compute the labor time variance.:

a: 9,880f

b: 9,880u

c: 7,800u

d: 7,800f

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 06:30
Select all that apply. select the ways that labor unions can increase wages. collective bargaining reducing the labor supply increasing the demand for labor creating monopolies
Answers: 1
question
Business, 22.06.2019 09:00
You speak to a business owner that is taking in almost $2000 in revenue each month. the owner still says that they are having trouble keeping the doors open. how can that be possible? use the terms of revenue, expenses and profit/loss in your answer
Answers: 3
question
Business, 22.06.2019 15:00
(a) what do you think will happen if the price of non-gm crops continues to rise? why? (b) what will happen if the price of non-gm food drops? why?
Answers: 2
question
Business, 22.06.2019 20:00
Experienced problem solvers always consider both the value and units of their answer to a problem. why?
Answers: 3
You know the right answer?
The flapjack corporation had 8,200 actual direct labor hours at an actual rate of $12.40 per hour. o...
Questions
question
Mathematics, 08.04.2020 01:36
question
Engineering, 08.04.2020 01:37
Questions on the website: 13722361