All of the following elements should be included in a project scope statement except:
1. project boundaries or exclusions
2. names of the project team members
3. assumptions and constraints that may limit or influence project work
4. key deliverables with acceptance criteria

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 21:00
After discussing the options, the strategic management team has agreed that the pod coffee idea works well with the company's mission statement and decides that the company should move forward in exploring the pod coffee idea. in order to make sure that the pod coffee idea is a good one, and to see if there are other potential future endeavors to pursue, you must analyze the market situation and formulate a strategy. your boss asks you to start working on the pod coffee idea. what is your first stepa. your first step is to formulate a strategy for how to market the pod coffee concept. b. your first step is to consult with your boss and find out what he thinks about the pod coffee idea. c. your first step is to do some research to find out what your competitors are doing. d. your first step is to analyze the organization's strengths, weaknesses, opportunities, and threats.
Answers: 2
question
Business, 22.06.2019 01:30
The gomez company, a merchandising firm, has budgeted its activity for december according to the following information: • sales at $500,000, all for cash. • merchandise inventory on november 30 was $250,000. • the cash balance at december 1 was $20,000. • selling and administrative expenses are budgeted at $50,000 for december and are paid for in cash. • budgeted depreciation for december is $30,000. • the planned merchandise inventory on december 31 is $260,000. • the cost of goods sold represents 75% of the selling price. • all purchases are paid for in cash. the budgeted cash disbursements for december are:
Answers: 3
question
Business, 22.06.2019 03:00
What is the relationship between marginal external cost, marginal social cost, and marginal private cost? a. marginal social cost equals marginal private cost plus marginal external cost. b. marginal private cost plus marginal social cost equals marginal external cost. c. marginal social cost plus marginal external cost equals marginal private cost. d. marginal external cost equals marginal private cost minus marginal social cost. marginal external cost a. is expressed in dollars, so it is not an opportunity cost b. is an opportunity cost borne by someone other than the producer c. is equal to two times the marginal private cost d. is a convenient economics concept that is not real
Answers: 3
question
Business, 22.06.2019 07:10
Walsh company manufactures and sells one product. the following information pertains to each of the company’s first two years of operations: variable costs per unit: manufacturing: direct materials $ 25 direct labor $ 12 variable manufacturing overhead $ 5 variable selling and administrative $ 4 fixed costs per year: fixed manufacturing overhead $ 400,000 fixed selling and administrative expenses $ 60,000 during its first year of operations, walsh produced 50,000 units and sold 40,000 units. during its second year of operations, it produced 40,000 units and sold 50,000 units. the selling price of the company’s product is $83 per unit. required: 1. assume the company uses variable costing: a. compute the unit product cost for year 1 and year 2. b. prepare an income statement for year 1 and year 2. 2. assume the company uses absorption costing: a. compute the unit product cost for year 1 and year 2. b. prepare an income statement for year 1 and year 2. 3. reconcile the difference between variable costing and absorption costing net operating income in year 1.
Answers: 3
You know the right answer?
All of the following elements should be included in a project scope statement except:
1. pro...
Questions
Questions on the website: 13722367