subject
Business, 13.12.2019 20:31 stefan19367

Your firm is considering a project that will cost $ 4.548 million up front, generate cash flows of $ 3.50 million per year for 3 years, and then have a cleanup and shutdown cost of $ 6.00 million in the fourth year.

a. how many irrs does this project have?
b. calculate a modified irr for this project assuming a discount and compounding rate of 10.0 %.
c. using the mirr and a cost of capital of 10.0 %, would you take the project?
d. how many irrs does this project have?

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 19:40
Uppose stanley's office supply purchases 50,000 boxes of pens every year. ordering costs are $100 per order and carrying costs are $0.40 per box. moreover, management has determined that the eoq is 5,000 boxes. the vendor now offers a quantity discount of $0.20 per box if the company buys pens in order sizes of 10,000 boxes. determine the before-tax benefit or loss of accepting the quantity discount. (assume the carrying cost remains at $0.40 per box whether or not the discount is taken.)
Answers: 1
question
Business, 22.06.2019 00:00
Which part/word/phrase in the passage refers to a business’s financing activity seen in a cash flow statement? nathan works as an accountant in a footwear manufacturing company. he is currently preparing the cash flow statement for his employer. during the given accounting period, the company purchased raw materials worth $25,000. it also bought new equipment worth $75,000 to increase its production output. further, it borrowed a long-term bank loan of $100,000 to facilitate further expansion. finally, the company spent $50,000 on advertising its latest brand of footwear in the market. {lol i guessed its "it borrowed a long-term bank loan of $100,000 to facilitate further expansion" and thats correct}
Answers: 1
question
Business, 22.06.2019 08:00
Why is it vital to maintain a designer worksheet? a. it separates the designs chosen for the season from those rejected by the company. b. it keeps a record of all designs created by the designer for a season. c. it charts out the development of an entire line through the season and beyond. d. it tracks the development of a design along with costing and production details. done
Answers: 1
question
Business, 22.06.2019 20:00
Afirm is producing at minimum average total cost with its current plant. draw the firm's long-run average cost curve. label it. draw a point on the lrac curve at which the firm cannot lower its average total cost. draw the firm's short-run average total cost curve that is consistent with the point you have drawn. label it.g
Answers: 2
You know the right answer?
Your firm is considering a project that will cost $ 4.548 million up front, generate cash flows of $...
Questions
question
Social Studies, 29.07.2019 02:40
Questions on the website: 13722367