You are working as a project manager in your organization. you are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. for your project archives, which one of the following is an output of risk monitoring and control?
a. quantitative risk analysis
b. risk audits
c. requested changes
d. qualitative risk analysis

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 21:30
Problem 2-18 job-order costing for a service company [lo2-1, lo2-2, lo2-3]speedy auto repairs uses a job-order costing system. the company's direct materials consist of replacement parts installed in customer vehicles, and its direct labor consists of the mechanics' hourly wages. speedy's overhead costs include various items, such as the shop manager's salary, depreciation of equipment, utilities, insurance, and magazine subscriptions and refreshments for the waiting room. the company applies all of its overhead costs to jobs based on direct labor-hours. at the beginning of the year, it made the following estimates: direct labor-hours required to support estimated output 10,000fixed overhead cost $ 90,000variable overhead cost per direct labor-hour $ 1.00 required: 1. compute the predetermined overhead rate.2. during the year, mr. wilkes brought in his vehicle to replace his brakes, spark plugs, and tires. the following information was available with respect to his job: direct materials $ 600direct labor cost $ 180direct labor-hours used 2 compute mr. wilkes' total job cost. 3. if speedy establishes its selling prices using a markup percentage of 30% of its total job cost, then how much would it have charged mr. wilkes?
Answers: 1
question
Business, 22.06.2019 09:30
Factors like the unemployment rate, the stock market, global trade, economic policy, and the economic situation of other countries have no influence on the financial status of individuals. question 1 options: true false
Answers: 1
question
Business, 22.06.2019 11:00
You decide to invest in a portfolio consisting of 25 percent stock a, 25 percent stock b, and the remainder in stock c. based on the following information, what is the expected return of your portfolio? state of economy probability of state return if state occurs of economy stock a stock b stock c recession .16 - 16.4 % - 2.7 % - 21.6 % normal .55 12.6 % 7.3 % 15.9 % boom .29 26.2 % 14.6 % 30.5 %
Answers: 1
question
Business, 22.06.2019 17:30
What do you think: would it be more profitable to own 200 shares of penny’s pickles or 1 share of exxon? why do you think that?
Answers: 1
You know the right answer?
You are working as a project manager in your organization. you are nearing the final stages of proje...
Questions
question
Mathematics, 21.02.2020 06:13
question
Mathematics, 21.02.2020 06:14
Questions on the website: 13722362