subject
Business, 28.12.2019 05:31 abbygreen

The following data are for a series of increasingly extensive flood-control projects.
total cost per year total benefit per year
plan a = levees $10,000 $16,000
plan b = small reservoir 24,000 36,000
plan c = medium reservoir 44,000 52,000
plan d = large reservoir 72,000 64,000
for plan d marginal costs and marginal benefits are
$16,000 and $28,000, respectively.
$24,000 and $18,000, respectively.
$28,000 and $12,000, respectively.
$72,000 and $64,000, respectively.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 08:30
Uppose that the federal reserve purchases a bond for $100,000 from donald truck, who deposits the proceeds in the manufacturer’s national bank. what will be the impact of this purchase on the supply of money? the money supply will increase by $100,000. the money supply will increase by $80,000. the money supply will increase by $500,000. this action will have no effect on the money supply. if the reserve requirement ratio is 20 percent, what is the maximum amount of additional loans that the manufacturer’s bank will be able to extend as the result of truck’s deposit? the maximum additional loans is $100,000. the maximum additional loans is $80,000. the maximum additional loans is $20,000. the maximum additional loans is $500,000. given the 20 percent reserve requirement, what is the maximum increase in the quantity of checkable deposits that could result throughout the entire banking system because of the fed’s action? this action will have no effect on the money supply. the money supply will eventually increase by $80,000. the money supply will eventually increase by $500,000. the money supply will eventually increase by $100,000.
Answers: 1
question
Business, 22.06.2019 13:10
Trey morgan is an employee who is paid monthly. for the month of january of the current year, he earned a total of $4,538. the fica tax for social security is 6.2% of the first $118,500 earned each calendar year, and the fica tax rate for medicare is 1.45% of all earnings for both the employee and the employer. the amount of federal income tax withheld from his earnings was $680.70. his net pay for the month is .
Answers: 1
question
Business, 22.06.2019 15:10
Paying attention to the purpose of her speech, which questions can she eliminate? a. 1 and 2 b. 3 c. 2 and 4 d. 1-4
Answers: 2
question
Business, 22.06.2019 20:30
Afirm wants to hire a project manager (pm) at a salary of $100,000. 30% of pms have high ability, and 70% of pms have low ability. high ability pms generate $120,000 in revenue and low ability pms generate $80,000 in revenue. in addition to differences in productivity, high and low ability pms have different outside offers. if a high ability pm is not hired by the firm, she can work for another company at a salary of $80,000. if the low ability pm is not hired by the firm, she can work for another company for $70,000. high ability pms are also able to get a project management professional (pmp) certification at a cost of $1,000. low ability pms are unable to get a pmp certification (they would fail the test). the firm is not able to observe a pm’s ability, but is able to observe and verify whether or not the pm has a pmp certificate.(a) draw the extensive form of the game.expert answer
Answers: 3
You know the right answer?
The following data are for a series of increasingly extensive flood-control projects.
total co...
Questions
question
Computers and Technology, 24.09.2019 11:00
question
Mathematics, 24.09.2019 11:00
Questions on the website: 13722367