The method used to collect information to use through all phases of the project life cycle is called

a. responsibility matrix
b. organization breakdown structure
c. work breakdown structure
d. priority matrix
e. work package

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 23:00
James has set the goal of achieving all "a"s during this year of school.which term best describes this goal
Answers: 2
question
Business, 21.06.2019 23:30
Renaldo scanlon is a financial consultant. he earns $30 per hour and works 32.5 hours a week. what is his straight-time pay?
Answers: 1
question
Business, 22.06.2019 19:00
Gus needs to purée his soup while it's still in the pot. what is the best tool for him to use? a. potato masher b. immersion blender c. rotary mixer d. whisk
Answers: 2
question
Business, 22.06.2019 21:30
An allergy products superstore buys 6000 of their most popular model of air filters each year. the price of the air filters is $18. the cost of ordering and receiving shipments is $12 per order. accounting estimates annual carrying costs are 20% of the price. the supplier lead time is 2 days. the store operates 240 days per year. each order is received from the supplier in a single delivery. there are no quantity discounts. what is the store’s minimum total annual cost of placing orders & carrying inventory?
Answers: 1
You know the right answer?
The method used to collect information to use through all phases of the project life cycle is called...
Questions
question
Mathematics, 03.02.2020 10:47
Questions on the website: 13722362