If a contractor is producing missiles for the navy, and the contractor fails to deliver them on time, the navy has the right to: [contrast the difference between termination for convenience, termination for default, and termination for cause.]

a. terminate the contract for default
b. terminate the contract for convenience
c. terminate the contract for cause
d. all of the answers are correct

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:30
Anewspaper boy is trying to perfect his business in order to maximize the money he can save for a new car. daily paper sales are normally distributed, with a mean of 100 and standard deviation of 10. he sells papers for $0.50 and pays $0.30 for them. unsold papers are trashed with no salvage value. how many papers should he order each day and what % of the time will he experience a stockout? are there any drawbacks to the order size proposed and how could the boy address such issues?
Answers: 3
question
Business, 22.06.2019 13:30
If the economy were in the contracting phase of the business cycle, how might that affect your ability to find work?
Answers: 2
question
Business, 22.06.2019 13:30
Presented below is information for annie company for the month of march 2018. cost of goods sold $245,000 rent expense $ 36,000 freight-out 7,000 sales discounts 8,000 insurance expense 5,000 sales returns and allowances 11,000 salaries and wages expense 63,000 sales revenue 410,000 instructions prepare the income statement.
Answers: 2
question
Business, 22.06.2019 16:30
Which of the following has the largest impact on opportunity cost
Answers: 2
You know the right answer?
If a contractor is producing missiles for the navy, and the contractor fails to deliver them on time...
Questions
question
Chemistry, 24.12.2019 04:31
question
Social Studies, 24.12.2019 04:31
Questions on the website: 13722367