The cost performance index (CPI): a. can be used to estimate the projected cost of completing the project. b. indicates that the planned and actual costs are equal if CPI is more than one. c. is the ratio of earned value to planned value. d. indicates that a project is under budget if CPI is less than one.

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 10:30
6carla would like to buy a dress, a dresser for her bedroom, and a home theater system. she has one month's worth of living expenses in her emergency fund. carla decides to save for the home theater system. did carla make the right decision? why or why not? a. yes; her emergency fund is full and the other items will probably be less expensive. b. yes; she could save more for her emergency fund, but the home theater will be harder to save for. c. no; she should save more for her emergency fund because she has saved less than the recommended amount. d. no; she should have bought the dress and dresser first because she could afford them right away. reset next
Answers: 2
question
Business, 22.06.2019 11:00
Using a cps-sample of 7,440 individuals, you estimate the following regression: = 20.91 - 2.61 x female where female is a binary variable that takes on the value of 1 for females and is 0 otherwise. the standard error on the coefficient on female is 0.25. the 95% confidence interval for the gender wage gap, or the amount that females earn less, is: a) [-3.10, -2.12] b) [18.30, 23.52] c) [-3.02, -2.20] d) [-1.96, -1.64]
Answers: 3
question
Business, 22.06.2019 13:10
Laval produces lamps and home lighting fixtures. its most popular product is a brushed aluminum desk lamp. this lamp is made from components shaped in the fabricating department and assembled in the assembly department. information related to the 22,000 desk lamps produced annually follows.direct materials $280,000direct labor fabricating department (8,000 dlh × $24 per dlh) $192,000assembly department (16,600 dlh × $26 per dlh) $431,600machine hours fabricating department $15,200mhassembly department $20,850mhexpected overhead cost and related data for the two production departments follow.fabricating assemblydirect labor hours 150,000dlh 295,000dlhmachine hours 161,000mh 128,000mhoverhead cost $400,000 430,000required1. determine the plantwide overhead rate for laval using direct labor hours as a base.2. determine the total manufacturing cost per unit for the aluminum desk lamp using the plantwide overhead rate.3. compute departmental overhead rates based on machine hours in the fabricating department and direct labor hours in the assembly department.4. use departmental overhead rates from requirement 3 to determine the total manufacturing cost per unit for the aluminum desk lamps.
Answers: 3
question
Business, 22.06.2019 17:20
“strategy, plans, and budgets are unrelated to one another.” do you agree? explain. explain how the manager’s choice of the type of responsibility center (cost, revenue, profit, or investment) affects the behavior of other employees.
Answers: 3
You know the right answer?
The cost performance index (CPI): a. can be used to estimate the projected cost of completing the pr...