Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that even though we should have (25/30) percent of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far $175,000 has actually been brought in on the project.

Calculate the schedule variance, schedule performance index, and cost (actually revenue in this case) variance and cost (actually revenue here) performance index. How is the project going?
Hint:Note that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:30
Afactory owner wants his workers to produce as many widgets as they can so he pays his workers based on how many widgets they produce. however, in order to make sure that the workers do not rush and produce a large number of poorly made widgets, he checks the widgets at random at various stages of their manufacture. if a defect is found in a widget, the pay of the entire section of the factory responsible for that defect is docked. how is this factory owner seeking to solve the agency conflict problem in this case?
Answers: 2
question
Business, 21.06.2019 22:30
Your project team’s recommendations to increase productivity have been approved and your team is now working on an implementation plan. in order to accomplish the plan, several subject matter experts from various parts of the organization have been brought in to assist. you have noticed friction and conflict among team members. some of the disagreement and opposition on your team supports the achievement of team goals and objectives. this type of conflict can be described as:
Answers: 1
question
Business, 22.06.2019 11:00
Abank provides its customers mobile applications that significantly simplify traditional banking activities. for example, a customer can use a smartphone to take a picture of a check and electronically deposit into an account. this unique service demonstrates the bank’s desire to practice which one of porter’s strategies?
Answers: 3
question
Business, 22.06.2019 13:30
On january 2, well co. purchased 10% of rea, inc.’s outstanding common shares for $400,000, which equaled the carrying amount and the fair value of the interest purchased in rea’s net assets. well did not elect the fair value option. because well is the largest single shareholder in rea, and well’s officers are a majority on rea’s board of directors, well exercises significant influence over rea. rea reported net income of $500,000 for the year and paid dividends of $150,000. in its december 31 balance sheet, what amount should well report as investment in rea?
Answers: 3
You know the right answer?
Your project to obtain charitable donations is now 30 days into a planned 40-day project. The projec...
Questions
question
Social Studies, 28.05.2021 08:30
question
Mathematics, 28.05.2021 08:30
Questions on the website: 13722359