An electronics manufacturer makes remote control devices for interactive-cable-TV systems. The following assembly tasks must be performed on each device.

Task Description Predecessor(s) Time (min.) A Place circuit into circuit frame -- 0.50 B Solder circuit connections to central A 0.70 . circuit control C Place circuit assembly in device frame B 0.40 D Attach circuit assembly to device frame C 0.30 E Place and attach display to frame -- 0.30 F Place and attach keypad to frame -- 0.20 G Place and attach top body of device to frame E, F 0.35 H Place and attach battery holder to frame D 0.40 I Place and attach bottom body of device G, H 0.60 . to frame J Test device I 0.30

(a) Draw the precedence diagram for this problem.
(b) What is the sum of the task times?
(c) What cycle time will allow the production of 200 units over a ten-hour day?
(d) What is the theoretical number of workstations needed?
(e) Balance this assembly line using the heuristic most following tasks and the heuristic longest operation time.
(f) How do these two solutions differ? Which do you prefer and why?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 01:10
Technology corp. is considering a $238,160 investment in a new marketing campaign that it anticipates will provide annual cash flows of $52,000 for the next five years. the firm has a 6% cost of capital. what should the analysis indicate to the firm's managers?
Answers: 2
question
Business, 22.06.2019 16:30
En major recording acts are able to play at the stadium. if the average profit margin for a concert is $175,000, how much would the stadium clear for all of these events combined?
Answers: 3
question
Business, 22.06.2019 17:40
Within the relevant range, if there is a change in the level of the cost driver, then a. total fixed costs will remain the same and total variable costs will change b. total fixed costs will change and total variable costs will remain the same c. total fixed costs and total variable costs will change d. total fixed costs and total variable costs will remain the same
Answers: 3
question
Business, 22.06.2019 18:00
Carlton industries is considering a new project that they plan to price at $74.00 per unit. the variable costs are estimated at $39.22 per unit and total fixed costs are estimated at $12,085. the initial investment required is $8,000 and the project has an estimated life of 4 years. the firm requires a return of 8 percent. ignore the effect of taxes. what is the degree of operating leverage at the financial break-even level of output?
Answers: 3
You know the right answer?
An electronics manufacturer makes remote control devices for interactive-cable-TV systems. The follo...
Questions
question
Mathematics, 11.10.2020 14:01
Questions on the website: 13722361