You are creating a schedule duration estimate for the activities in the PDR Project. You’re working with your project and comparing the results of a past similar project to predict the time of the current project. What estimating approach are you using?
A. Organizational process assets
B. Parametric
C. Analogous
D. PERT

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 12:10
Bonds often pay a coupon twice a year. for the valuation of bonds that make semiannual payments, the number of periods doubles, whereas the amount of cash flow decreases by half. using the values of cash flows and number of periods, the valuation model is adjusted accordingly. assume that a $1,000,000 par value, semiannual coupon us treasury note with three years to maturity has a coupon rate of 3%. the yield to maturity (ytm) of the bond is 7.70%. using this information and ignoring the other costs involved, calculate the value of the treasury note:
Answers: 1
question
Business, 22.06.2019 13:10
Trey morgan is an employee who is paid monthly. for the month of january of the current year, he earned a total of $4,538. the fica tax for social security is 6.2% of the first $118,500 earned each calendar year, and the fica tax rate for medicare is 1.45% of all earnings for both the employee and the employer. the amount of federal income tax withheld from his earnings was $680.70. his net pay for the month is .
Answers: 1
question
Business, 22.06.2019 14:00
Which of the following is not a characteristic of a weak economy? a. a low employment rateb. a high inflation ratec. a decreased gdpd. a high unemployment rate
Answers: 1
question
Business, 22.06.2019 14:10
Carey company is borrowing $225,000 for one year at 9.5 percent from second intrastate bank. the bank requires a 15 percent compensating balance. the principal refers to funds the firm can effectively utilize (amount borrowed − compensating balance). a. what is the effective rate of interest? (use a 360-day year. input your answer as a percent rounded to 2 decimal places.) b. what would the effective rate be if carey were required to make 12 equal monthly payments to retire the loan?
Answers: 1
You know the right answer?
You are creating a schedule duration estimate for the activities in the PDR Project. You’re working...
Questions
question
Mathematics, 26.05.2020 06:59
question
English, 26.05.2020 06:59
question
English, 26.05.2020 06:59
question
Mathematics, 26.05.2020 06:59
question
Geography, 26.05.2020 06:59
question
Mathematics, 26.05.2020 06:59
question
Mathematics, 26.05.2020 07:00
Questions on the website: 13722360