A project costs $91,000 today and is expected to generate cash flows of $11,000 per year for the next 20years. The firm has a cost of capital of 8 percent. Should this project be accepted, and why?

A. Yes, the project should be accepted since it has a NPV = $15,391.23.

B. Yes, the project should be accepted since it has a NPV = $13,610.89.

C. Yes, the project should be accepted since it has a NPV = $16,999.62.

D. None of these answers is correct.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 16:30
ernst's electrical has a bond issue outstanding with ten years to maturity. these bonds have a $1,000 face value, a 5 percent coupon, and pay interest semiminusannually. the bonds are currently quoted at 96 percent of face value. what is ernst's pretax cost of debt?
Answers: 1
question
Business, 22.06.2019 04:40
Select the correct answerwhat is the responsibility of each of the twelve federal reserve's banks in their districts? a.they set the prime rateob.they monitor functioning of banks in their through onsite and offsite reviewsc.they assess taxes in their destnictd.they write fiscal policies
Answers: 1
question
Business, 22.06.2019 14:30
In our daily interactions we can find ourselves listening to other people solely for the purpose of finding weakness in their positions so that we can formulate a convincing response. select one: true false
Answers: 1
question
Business, 22.06.2019 18:30
What is the relationship between credit and debt?
Answers: 1
You know the right answer?
A project costs $91,000 today and is expected to generate cash flows of $11,000 per year for the nex...
Questions
question
Mathematics, 23.03.2021 18:00
question
Health, 23.03.2021 18:10
question
Mathematics, 23.03.2021 18:10
question
Mathematics, 23.03.2021 18:10
question
English, 23.03.2021 18:10
question
Mathematics, 23.03.2021 18:10
Questions on the website: 13722359