A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance .33), and D (variance .17). What is the standard deviation on the critical path?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 19:30
Maker-bot corporation has 10,000 shares of 10%, $90 par value, cumulative preferred stock outstanding since its inception. no dividends were declared in the first two years. if the company pays $400,000 of dividends in the third year, how much will common stockholders receive?
Answers: 2
question
Business, 22.06.2019 11:00
Consider an economy where government expenditures are 10 and total tax revenues are 10. the supply of labor is fixed at 125 and the supply of capital is fixed at 8. the economy is described by the following equations. y k to the power of 1 divided by 3 end exponent l to the power of 2 divided by 3 end exponent c 2.5 + 0.75 ( y - t ) i 10 - 0.5 r the level of private savings is
Answers: 1
question
Business, 22.06.2019 20:00
The master manufacturing company has just announced a tender offer for its own common stock. master is offering to buy up to 100% of the company's stock at $20 per share contingent on at least 64% of the outstanding shares being tendered. after the announcement of the offer, the stock closed on the nyse up 2.50 at $18.75. a customer has 100 shares of master stock in his cash account. the customer tells you that he wishes to "cash out" his position. you should recommend that the customer:
Answers: 2
question
Business, 22.06.2019 21:00
Suppose either computers or televisions can be assembled with the following labor inputs: units produced 1 2 3 4 5 6 7 8 9 10 total labor used 3 7 12 18 25 33 42 54 70 90 (a) draw the production possibilities curve for an economy with 54 units of labor. label it p54. (b) what is the opportunity cost of the eighth computer? (c) suppose immigration brings in 36 more workers. redraw the production possibilities curve to reflect this added labor. label the new curve p90.
Answers: 2
You know the right answer?
A project’s critical path is composed of activities A (variance .33), B (variance .67), C (variance...
Questions
question
Mathematics, 05.03.2021 21:30
question
Mathematics, 05.03.2021 21:30
question
History, 05.03.2021 21:30
question
SAT, 05.03.2021 21:30
Questions on the website: 13722362