A certain project has ten activities. Two activities each have a total slack of 5 days. The total duration of the project’s critical path is 40 days. The duration of the project is .

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 19:50
What is the present value of the following cash flow stream at a rate of 12.0%? years: 0 1 2 3 4| | | | |cfs: $0 $1,500 $3,000 $4,500 $6,000a. $9,699b. $10,210c. $10,747d. $11,284e. $11,849
Answers: 3
question
Business, 22.06.2019 20:00
Later movers do not face: entrenched competitors. reduced uncertainty over technologies. high growth markets. lower market uncertainty.
Answers: 3
question
Business, 22.06.2019 22:00
Acompany's sales in year 1 were $300,000, year 2 were $351,000, and year 3 were $400,000. using year 2 as a base year, the sales percent for year 3 is
Answers: 2
question
Business, 23.06.2019 02:00
How much more output does the $18 trillion u.s. economy produce when gdp increases by 3.0 percen?
Answers: 1
You know the right answer?
A certain project has ten activities. Two activities each have a total slack of 5 days. The total du...
Questions
Questions on the website: 13722359