Business, 12.03.2020 02:06 asorrell5075

An activity on a project schedule has these duration estimates: optimistic (a) = 1, most likely (m) = 2, and pessimistic (b) = 5. The activity’s expected duration is:

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 10:50
Kimberly has been jonah in preparing his personal income tax forms for a couple of years. jonah's boss recommended kimberly because she had done a good job setting up the company's new accounting system. jonah is very satisfied with kimberly's work and feels that the fees she charges are quite reasonable. kimberly would be classified as a(n) (a) independent auditor (b) private accountant (c) public accountant (d) accounting broker
Answers: 1
question
Business, 22.06.2019 14:50
Ann chovies, owner of the perfect pasta pizza parlor, uses 20 pounds of pepperoni each day in preparing pizzas. order costs for pepperoni are $10.00 per order, and carrying costs are 4 cents per pound per day. lead time for each order is three days, and the pepperoni itself costs $3.00 per pound. if she were to order 80 pounds of pepperoni at a time, what would be the average inventory level?
Answers: 3
question
Business, 22.06.2019 22:00
Exercise 2-12 cost behavior; high-low method [lo2-3, lo2-4] speedy parcel service operates a fleet of delivery trucks in a large metropolitan area. a careful study by the company’s cost analyst has determined that if a truck is driven 120,000 miles during a year, the average operating cost is 11.6 cents per mile. if a truck is driven only 80,000 miles during a year, the average operating cost increases to 13.6 cents per mile. required: 1.& 2. using the high-low method, estimate the variable and fixed cost elements of the annual cost of truck operation. (round the "variable cost per mile" to 3 decimal places.)
Answers: 3
question
Business, 22.06.2019 23:20
Nnette henri is paid an hourly wage of $8.90 for a 32-hour workweek of 4 days, 8 hours daily. for any work on the fifth day and on saturdays, she is paid one and one-half times her regular hourly rate. during a certain week, in addition to her regular 32 hours, henri worked 6 hours on the fifth day and 5 hours on saturday. for this workweek, henri’s total earnings are:
Answers: 1
You know the right answer?
An activity on a project schedule has these duration estimates: optimistic (a) = 1, most likely (m)...
Questions
question
Biology, 04.11.2020 23:30
question
Physics, 04.11.2020 23:30
question
Mathematics, 04.11.2020 23:30
Questions on the website: 13722367