An assembly line consists of 21 tasks grouped into 5 workstations. The sum of the 21 task times is 90 minutes. The largest assigned cycle time is 20 minutes. What is the efficiency of this line?

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 12:30
Suppose a holiday inn hotel has annual fixed costs applicable to its rooms of $1.2 million for its 300-room hotel, average daily room rents of $50, and average variable costs of $10 for each room rented. it operates 365 days per year. the amount of operating income on rooms, assuming an occupancy* rate of 80% for the year, that will be generated for the entire year is *occupancy = % of rooms rented
Answers: 1
question
Business, 22.06.2019 17:40
Within the relevant range, if there is a change in the level of the cost driver, then a. total fixed costs will remain the same and total variable costs will change b. total fixed costs will change and total variable costs will remain the same c. total fixed costs and total variable costs will change d. total fixed costs and total variable costs will remain the same
Answers: 3
question
Business, 22.06.2019 19:00
Question 55 ted, a supervisor for jack's pool supplies, was accused of stealing pool supplies and selling them to friends and relatives at reduced prices. given ted's earlier track record, he was not fired immediately. the authorities decided to give him an administrative leave, without pay, until the investigation was complete. in view of the given information, it would be most appropriate to say that ted was: demoted. discharged. suspended. dismissed.
Answers: 2
question
Business, 22.06.2019 19:10
You have just been hired as a brand manager at kelsey-white, an american multinational consumer goods company. recently the firm invested in the development of k-w vision, a series of systems and processes that allow the use of up-to-date data and advanced analytics to drive informed decision making about k-w brands. it is 2018. the system is populated with 3 years of historical data. as brand manager for k-w’s blue laundry detergent, you are tasked to lead the brand's turnaround. use the vision platform to to develop your strategy and grow blue’s market share over the next 4 years.
Answers: 2
You know the right answer?
An assembly line consists of 21 tasks grouped into 5 workstations. The sum of the 21 task times is 9...
Questions
question
English, 02.01.2021 05:40
question
Mathematics, 02.01.2021 05:40
question
Mathematics, 02.01.2021 05:40
question
Mathematics, 02.01.2021 05:40
question
Social Studies, 02.01.2021 05:40
Questions on the website: 13722361