Business, 14.03.2020 00:17 breanastone14

Manton Corporation uses an activity based costing system to assign overhead costs to products. In the first stage, two overhead costs—equipment expense and indirect labor—are allocated to the three activity cost pools—Processing, Supervising, and Other—based on resource consumption. Data to perform these allocations appear below:

Overhead costs:
Equipment expense $ 54,500
Indirect labor 9,900
Distribution of Resource Consumption Across Activity Cost Pools:
Activity Cost Pools
Processing Supervising Other
Equipment expense 0.60 0.20 0.20
Indirect labor 0.10 0.30 0.60

In the second stage, Processing costs are assigned to products using machine-hours (MHs) and Supervising costs are assigned to products using the number of batches. The costs in the Other activity cost pool are not assigned to products. Activity data for the company's two products follow:

Activity:
MHs (Processing) Batches (Supervising)
Product Z5 6,670 2,160
Product C8 16,330 1,440
Total 23,000 3,600

How much overhead cost is allocated to the Processing activity cost pool under activity-based costing in the first stage of allocation?

a. $32,700

b. $33,690

c. $990

d. $9,690

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 23:30
San ruiz interiors provides design services to residential and commercial clients. the residential services produce a contribution margin of $450,000 and have traceable fixed operating costs of $480,000. management is studying whether to drop the residential operation. if closed, the fixed operating costs will fall by $370,000 and san ruiz’ income will
Answers: 3
question
Business, 22.06.2019 10:50
Suppose that a firm is considering moving from a batch process to an assembly-line process to better meet evolving market needs. what concerns might the following functions have about this proposed process change: marketing, finance, human resources, accounting, and information systems?
Answers: 2
question
Business, 22.06.2019 16:20
Carlos hears juan and rita’s complaints about the new employees with whom they have to work with, as well as their threats to quit the company. if carlos were to reassign juan and rita to new, unique roles and separate them from the ronny and bill, it would signal that carlos has moved into the stage of managing resistance.
Answers: 3
question
Business, 22.06.2019 17:40
Turrubiates corporation makes a product that uses a material with the following standards standard quantity 8.0 liters per unit standard price $2.50 per liter standard cost $20.00 per unit the company budgeted for production of 3,800 units in april, but actual production was 3,900 units. the company used 32,000 liters of direct material to produce this output. the company purchased 20,100 liters of the direct material at $2.6 per liter. the direct materials purchases variance is computed when the materials are purchased. the materials quantity variance for april is:
Answers: 1
You know the right answer?
Manton Corporation uses an activity based costing system to assign overhead costs to products. In th...
Questions
question
Mathematics, 10.09.2020 04:01
question
Geography, 10.09.2020 04:01
question
Mathematics, 10.09.2020 04:01
question
Mathematics, 10.09.2020 04:01
question
Biology, 10.09.2020 04:01
question
English, 10.09.2020 04:01
question
English, 10.09.2020 04:01
question
Mathematics, 10.09.2020 04:01
question
Mathematics, 10.09.2020 04:01
question
English, 10.09.2020 04:01
question
Mathematics, 10.09.2020 04:01
question
Mathematics, 10.09.2020 04:01
question
Mathematics, 10.09.2020 04:01
question
Geography, 10.09.2020 04:01
question
Mathematics, 10.09.2020 04:01
question
Chemistry, 10.09.2020 04:01
question
Mathematics, 10.09.2020 04:01
Questions on the website: 13722360