A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 14:00
Which is part of the sales process? a. customer retention b. billing c. cost planning d. customer relations
Answers: 1
question
Business, 22.06.2019 07:40
Shelby company produces three products: product x, product y, and product z. data concerning the three products follow (per unit): product x product y product z selling price $ 85 $ 65 $ 75 variable expenses: direct materials 25.50 19.50 5.25 labor and overhead 25.50 29.25 47.25 total variable expenses 51.00 48.75 52.50 contribution margin $ 34.00 $ 16.25 $ 22.50 contribution margin ratio 40 % 25 % 30 % demand for the company’s products is very strong, with far more orders each month than the company can produce with the available raw materials. the same material is used in each product. the material costs $8 per pound, with a maximum of 4,400 pounds available each month. required: a. compute contribution margin per pound of materials used. (round your intermediate calculations and final answers to 2 decimal places.) contribution margin per pound product x $ product y $ product z $ b. which orders would you advise the company to accept first, those for product x, for product y, or for product z? which orders second? third? product x product y product z
Answers: 3
question
Business, 22.06.2019 11:10
Suppose that the firm cherryblossom has an orchard they are willing to sell today. the net annual returns to the orchard are expected to be $50,000 per year for the next 20 years. at the end of 20 years, it is expected the land will sell for $30,000. calculate the market value of the orchard if the market rate of return on comparable investments is 16%.
Answers: 1
question
Business, 22.06.2019 13:10
Thomas kratzer is the purchasing manager for the headquarters of a large insurance company chain with a central inventory operation. thomas's fastest-moving inventory item has a demand of 6,000 units per year. the cost of each unit is $100, and the inventory carrying cost is $10 per unit per year. the average ordering cost is $30 per order. it takes about 5 days for an order to arrive, and the demand for 1 week is 120 units. (this is a corporate operation, and the are 250 working days per year.)a) what is the eoq? b) what is the average inventory if the eoq is used? c) what is the optimal number of orders per year? d) what is the optimal number of days in between any two orders? e) what is the annual cost of ordering and holding inventory? f) what is the total annual inventory cost, including cost of the 6,000 units?
Answers: 3
You know the right answer?
A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000....
Questions
question
Mathematics, 02.09.2019 15:30
Questions on the website: 13722363