A process produces two types of products A and B. Product A is done in batches of 1000 units. It involves a setup time of 2 hours and a run time of 75 seconds. Product B is done in batches of 500 units and involves a setup time of 1 hour and a run time of 45 seconds.

How many units can this process produce in a week of 40 hours, if:

only product A is produced?
only product B is produced?
A and B are produced in a mix of 25% A and 75% B?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 10:10
At the end of year 2, retained earnings for the baker company was $3,550. revenue earned by the company in year 2 was $3,800, expenses paid during the period were $2,000, and dividends paid during the period were $1,400. based on this information alone, retained earnings at the beginning of year 2 was:
Answers: 1
question
Business, 22.06.2019 12:30
Sales at a fast-food restaurant average $6,000 per day. the restaurant decided to introduce an advertising campaign to increase daily sales. to determine the effectiveness of the advertising campaign, a sample of 49 days of sales were taken. they found that the average daily sales were $6,300 per day. from past history, the restaurant knew that its population standard deviation is about $1,000. if the level of significance is 0.01, have sales increased as a result of the advertising campaign? multiple choicea)fail to reject the null hypothesis.b)reject the null hypothesis and conclude the mean is higher than $6,000 per day.c)reject the null hypothesis and conclude the mean is lower than $6,000 per day.d)reject the null hypothesis and conclude that the mean is equal to $6,000 per day.expert answer
Answers: 3
question
Business, 22.06.2019 23:00
Draw a flowchart for a process of interest to you, such as a quick oil-change service, a factory process you might have worked in, ordering a pizza, renting a car or truck, buying products on the internet, or applying for an automobile loan. identify the points where something (people, information) waits for service or is held in work-in-process inventory, the estimated time to accomplish each activity in the process, and the total flow time. evaluate how well the process worked and what might be done to improve it.
Answers: 2
question
Business, 23.06.2019 02:00
Create a list of five action verbs you might use on a job application to describe skills and/or work history. here are some examples: (organized, produced, selected, coordinated, contributed). find five other than the examples.
Answers: 3
You know the right answer?
A process produces two types of products A and B. Product A is done in batches of 1000 units. It inv...
Questions
question
Mathematics, 24.03.2020 21:01
question
Mathematics, 24.03.2020 21:01
Questions on the website: 13722363