A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and schedule variances and CSI? Estimate the time variance.

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 21:30
Afreezer manufacturer might purchase sheets of steel, wiring, shelving, and so forth, as part of its final product. this is an example of what sub-classification of business market?
Answers: 1
question
Business, 22.06.2019 06:00
For 2018, rahal's auto parts estimates bad debt expense at 1% of credit sales. the company reported accounts receivable and an allowance for uncollectible accounts of $86,500 and $2,100, respectively, at december 31, 2017. during 2018, rahal's credit sales and collections were $404,000 and $408,000, respectively, and $2,340 in accounts receivable were written off.rahal's accounts receivable at december 31, 2018, are:
Answers: 2
question
Business, 22.06.2019 06:40
After the 2008 recession, the amount of reserves in the us banking system increased. because of federal reserve actions, required reserves increased from $44 billion to $60 billion. however, banks started holding more reserves than required. by january 2009, banks were holding $900 billion in excess reserves. the federal reserve started paying interest on the excess reserves that the banks held. what possible impact will these unused reserves have on the economy?
Answers: 1
question
Business, 22.06.2019 10:00
Marco works in the marketing department of a luxury fashion brand. he is making a presentation on the success of a recent marketing campaign that included a fashion show. which slide elements can he use to include photographs and footage of the fashion show in his presentation? marco can use the: table images audio option to include photographs and the: flowcharts images video option to include footage of the fashion show.
Answers: 1
You know the right answer?
A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of...
Questions
question
Mathematics, 15.12.2019 14:31
question
Social Studies, 15.12.2019 14:31
Questions on the website: 13722362