It costs $75 per day for each day that a construction crew is on site. The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity. Use this information to determine the lowest cost for this project. All times given are in days. Activity Predecessor TUOL Ontol Normal Minimum Crash Cost Time Time |$/day) 10 16 $70 16 3 $40 2 2 - 4 2 $60 $80 8 15 ($90 ONNA C 1 DE
a.$1,750
b.$1,720
c.$1,810
d.$1,780

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 03:00
Journalize the following transactions that occurred in september 2015 for aquamarines. no explanations are needed. identify each accounts payable and accounts receivable with the vendor or customer name. sep. 3 purchased merchandise inventory on account from shallin wholesalers, $5,000. terms 1/15, n/eom, fob shipping point. 4 paid freight bill of $80 on september 3 purchase. 4 purchased merchandise inventory for cash of $1,700. 6 returned $500 of inventory from september 3 purchase. 8 sold merchandise inventory to hermosa company, $6,000, on account. terms 2/15, n/35. cost of goods, $2,640. 9 purchased merchandise inventory on account from thomas wholesalers, $8,000. terms 2/10, n/30, fob destination. 10 made payment to shallin wholesalers for goods purchased on september 3, less return and discount. 12 received payment from hermosa company, less discount. 13 after negotiations, received a $200 allowance from thomas wholesalers. 15 sold merchandise inventory to jordan company, $2,500, on account. terms 1/10, n/eom. cost of goods, $1,050. 22 made payment, less allowance, to thomas wholesalers for goods purchased on september 9. 23 jordan company returned $400 of the merchandise sold on september 15. cost of goods, $160. 25 sold merchandise inventory to smithsons for $1,100 on account that cost $400. terms of 2/10, n/30 were offered, fob shipping point. as a courtesy to smithsons, $75 of freight was added to the invoice for which cash was paid by aquamarines. 26 after negotiations, granted a $100 allowance to smithsons for merchandise purchased on september 25. 29 received payment from smithsons, less allowance and discount. 30 received payment from jordan company, less return.
Answers: 2
question
Business, 22.06.2019 08:40
Examine the following book-value balance sheet for university products inc. the preferred stock currently sells for $30 per share and pays a dividend of $3 a share. the common stock sells for $16 per share and has a beta of 0.9. there are 2 million common shares outstanding. the market risk premium is 9%, the risk-free rate is 5%, and the firm’s tax rate is 40%. book-value balance sheet (figures in $ millions) assets liabilities and net worth cash and short-term securities $ 2.0 bonds, coupon = 6%, paid annually (maturity = 10 years, current yield to maturity = 8%) $ 5.0 accounts receivable 3.0 preferred stock (par value $15 per share) 3.0 inventories 7.0 common stock (par value $0.20) 0.4 plant and equipment 21.0 additional paid-in stockholders’ equity 13.6 retained earnings 11.0 total $ 33.0 total $ 33.0 a. what is the market debt-to-value ratio of the firm? (do not round intermediate calculations. enter your answer as a percent rounded to 2 decimal places.) b. what is university’s wacc? (do not round intermediate calculations. enter your answer as a percent rounded to 2 decimal places.)
Answers: 3
question
Business, 22.06.2019 10:00
mary's baskets company expects to manufacture and sell 30,000 baskets in 2019 for $5 each. there are 4,000 baskets in beginning finished goods inventory with target ending inventory of 4,000 baskets. the company keeps no work-in-process inventory. what amount of sales revenue will be reported on the 2019 budgeted income statement?
Answers: 2
question
Business, 23.06.2019 00:10
Warren company plans to depreciate a new building using the double declining-balance depreciation method. the building cost $870,000. the estimated residual value of the building is $57,000 and it has an expected useful life of 20 years. assuming the first year's depreciation expense was recorded properly, what would be the amount of depreciation expense for the second year?
Answers: 2
You know the right answer?
It costs $75 per day for each day that a construction crew is on site. The project manager determine...
Questions
question
Mathematics, 25.01.2020 16:31
Questions on the website: 13722359