Holt Company enters into a contract to build a new plant facility for Segal Company for $2,500,000. In the contract, Segal will pay a performance bonus of $100,000 if Holt is able to complete the facility by October 1, 20X6. The performance bonus is reduced by 50% for each of the first two weeks after October 1, 20X6. If the completion is delayed more than two weeks, then Holt forfeits the entire performance bonus. Holt's prior experience with performance bonuses on similar contracts indicates the following probabilities of completion outcomes: The slide shows the following text: Completed by October 1, 2006 and its probability is 80%, Completed by October 8, 2006 and its probability is 10%, Completed by October 15, 2006 and its probability is 5%, and Completed after October 15, 2006 and its probability is 5%.
How much should Holt record as the transaction price of the contract and why?
a) $2,500,000 because the performance bonus is not guaranteed
b) $2,600,000 because the most likely outcome is that Holt will deliver the facility by October 1, 20X6
c) $2,461,250 because Holt should use the expected cost method
d) $2,586,250 because Holt should use the expected value method

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 06:00
For 2018, rahal's auto parts estimates bad debt expense at 1% of credit sales. the company reported accounts receivable and an allowance for uncollectible accounts of $86,500 and $2,100, respectively, at december 31, 2017. during 2018, rahal's credit sales and collections were $404,000 and $408,000, respectively, and $2,340 in accounts receivable were written off.rahal's accounts receivable at december 31, 2018, are:
Answers: 2
question
Business, 22.06.2019 19:30
The owner of firewood to go is considering buying a hydraulic wood splitter which sells for $50,000. he figures it will cost an additional $100 per cord to purchase and split wood with this machine, while he can sell each cord of split wood for $125. if, for this machine, design capacity is 50 cords per day, effective capacity is 40 cords per day, and actual output is expected to be 32 cords per day, what would be its efficiency?
Answers: 1
question
Business, 22.06.2019 20:00
During the month of march 2017, weimar world, a tax-preparation service, had the following transactions. * billed $496,000 in revenues on credit * received $164,000 from customers' accounts receivable * incurred expenses of $194,000 but only paid $87,700 cash for these expenses * prepaid $32,220 for computer services to be used next month what was the company's accrual basis net income for the month? select one: a. $302,000 b. $264,080 c. $ 41,860 d. $408,300 e. none of the above
Answers: 3
question
Business, 22.06.2019 20:40
Review the wbs and gantt chart you created previously. propose three to five additional activities that would you estimate resources and durations. now, identify at least eight milestones for the recreation and wellness intranet project. remember that milestones normally have no duration, so you must have tasks that will lead to completing the milestone. add your activities and milestones to your gantt chart, creating a new gantt chart. estimate the task durations and enter dependencies as appropriate. remember that your schedule goal for the project is six months. copy the gantt chart and network diagram to a word document.
Answers: 2
You know the right answer?
Holt Company enters into a contract to build a new plant facility for Segal Company for $2,500,000....
Questions
question
Social Studies, 28.01.2020 08:31
question
Mathematics, 28.01.2020 08:31
Questions on the website: 13722363