As part of a time study a particular job was analyzed. The study included 20 job cycles and the following cumulative times and performance rating factors for each element were reported St (min) 54.64 49.67 42.98 51.37 RF 1.05 1.10 0.95 0.95 Element 4 Assuming an allowance factor of 20% the standard time for this job would be .

A. 16.58 minutes
B. 12.10 minutes
C. 10-08 minutes
D. 14.73 minutes

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 01:30
What is an example of a good stock to buy during economic expansion? a) cyclical stock b) defensive stock c) income stock d) bond
Answers: 3
question
Business, 22.06.2019 13:30
1. is the act of declaring a drivers license void and terminated when it is determined that the license was issued through error or fraud.
Answers: 2
question
Business, 22.06.2019 15:30
The school cafeteria can make pizza for approximately $0.30 a slice. the cost of kitchen use and cafeteria staff runs about $200 per day. the pizza den nearby will deliver whole pizzas for $9.00 each. the cafeteria staff cuts the pizza into eight slices and serves them in the usual cafeteria line. with no cooking duties, the staff can be reduced by half, for a fixed cost of $75 per day. should the school cafeteria make or buy its pizzas?
Answers: 3
question
Business, 23.06.2019 02:00
When watching the video example 87: function notation, the presenter states that we need to, "go to this function and in the place of x, we will put in " â4 â3 â2 â1?
Answers: 3
You know the right answer?
As part of a time study a particular job was analyzed. The study included 20 job cycles and the foll...
Questions
question
History, 23.08.2019 18:30
question
English, 23.08.2019 18:30
Questions on the website: 13722361