An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9, and a late finish (LF) of day 19. Is the activity on the critical path? Explain. An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9, and a late finish (LF) of day 19. Is the activity on the critical path? Explain.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 21:20
Abakery wants to determine how many trays of doughnuts it should prepare each day. demand is normal with a mean of 5 trays and standard deviation of 1 tray. if the owner wants a service level of at least 95%, how many trays should he prepare (rounded to the nearest whole tray)? assume doughnuts have no salvage value after the day is complete.
Answers: 2
question
Business, 22.06.2019 10:50
Suppose that a firm is considering moving from a batch process to an assembly-line process to better meet evolving market needs. what concerns might the following functions have about this proposed process change: marketing, finance, human resources, accounting, and information systems?
Answers: 2
question
Business, 22.06.2019 12:20
If jobs have been undercosted due to underallocation of manufacturing overhead, then cost of goods sold (cogs) is too low and which of the following corrections must be made? a. decrease cogs for double the amount of the underallocation b. increase cogs for double the amount of the underallocation c. decrease cogs for the amount of the underallocation d. increase cogs for the amount of the underallocation
Answers: 3
question
Business, 22.06.2019 12:40
Kumar consulting operates several stock investment portfolios that are used by firms for investment of pension plan assets. last year, one portfolio had a realized return of 12.6 percent and a beta coefficient of 1.15. the average t-bond rate was 7 percent and the realized rate of return on the s& p 500 was 12 percent. what was the portfolio's alpha?
Answers: 1
You know the right answer?
An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of d...
Questions
question
Mathematics, 30.03.2020 18:41
question
Mathematics, 30.03.2020 18:41
Questions on the website: 13722367