Business, 24.03.2020 01:36 anaaaa46

A machine has a setup time of 150 minutes and run time of 0.0075 minutes per piece. Order sizes are typically 10,000 pieces. After a batch is processed, the process has to be stopped and the machine has to be setup before the next batch can be processed. Assume that a day consists of two shifts and each shift is 450 minutes long.

Find the capacity in pieces per day for this machine under the following assumptions:

a. A batch can consist of only one order; it cannot have other orders in it. (8 pts)

b. Three orders are combined to form a batch. (8 pts)

c. All orders can be combined into one batch. (8 pts)

d. What is the percent change in capacity as you go from a to b to c? (6 pts)

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 07:30
Hours to produce one unit worker hours to produce yarn country a 8 hours country b 4 hours worker hours to produce fabric counrty a 12 hours country b 13 hours additional worker hours to produce fabric instead of yarn country a ? country b? which of the follow is true of the trade relationship between country a and country b? country a has an absolute advantage in producing yarn and fabric country b has an absolute advantage in producing yarn and fabric country b has a comparative advantage to country a in producing fabric country a has a comparative advantage to country b in producing fabric
Answers: 2
question
Business, 22.06.2019 12:30
Provide an example of open-ended credit account that caroline has. caroline blue's credit report worksheet.
Answers: 1
question
Business, 22.06.2019 16:00
Arnold rossiter is a 40-year-old employee of the barrington company who will retire at age 60 and expects to live to age 75. the firm has promised a retirement income of $20,000 at the end of each year following retirement until death. the firm's pension fund is expected to earn 7 percent annually on its assets and the firm uses 7% to discount pension benefits. what is barrington's annual pension contribution to the nearest dollar for mr. rossiter? (assume certainty and end-of-year cash flows.)
Answers: 2
question
Business, 22.06.2019 16:50
Atrough in the business cycle occurs when
Answers: 1
You know the right answer?
A machine has a setup time of 150 minutes and run time of 0.0075 minutes per piece. Order sizes are...
Questions
question
Mathematics, 11.10.2019 19:30
question
Social Studies, 11.10.2019 19:30
question
Mathematics, 11.10.2019 19:30
Questions on the website: 13722367