Southern Industries uses a job order costing. The following information was drawn from the Company’s monthly accounting reports:
Job 1 Job 2 Job 3
Direct Materials $ 50 $ 60 $ 30
Direct Labor 20 30 10
Southern applies overhead at a rate of 100% of direct labor costs. By the end of the month, both Job 1 and Job 2 had been completed and sold. Job 3 was still in process. At month-end, what was the balance in the Work in Process inventory?
a. $260
b. $60
c. $40
d. $140

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 19:10
Goals that are overly ambitious can discourage employees and decrease motivation, yet the idea of stretch goals is proposed as a way to get people fired up and motivated. as a manager, how might you decide where to draw the line between a “good” stretch goal and a “bad” one that is unrealistic?
Answers: 1
question
Business, 22.06.2019 04:10
An outside manufacturer has offered to produce 60,000 daks and ship them directly to andretti's customers. if andretti company accepts this offer, the facilities that it uses to produce daks would be idle; however, fixed manufacturing overhead costs would be reduced by 75%. because the outside manufacturer would pay for all shipping costs, the variable selling expenses would be only two-thirds of their present amount. what is andretti's avoidable cost per unit that it should compare to the price quoted by the outside manufacturer?
Answers: 3
question
Business, 22.06.2019 22:00
Suppose that a paving company produces paved parking spaces (q) using a fixed quantity of land (t) and variable quantities of cement (c) and labor (l). the firm is currently paving 1,000 parking spaces. the firm's cost of cement is $3 comma 600.003,600.00 per acre covered (c) and its cost of labor is $35.0035.00/hour (w). for the quantities of c and l that the firm has chosen, mp subscript upper c baseline equals 60mpc=60 and mp subscript upper l baseline equals 7mpl=7. is this firm minimizing its cost of producing parking spaces?
Answers: 3
question
Business, 23.06.2019 14:30
Problem 1. the following balance sheet contains errors. lopez services,inc. balance sheet for the year ended december 31, 20-- assets liabilities current assets: current liabilities: cash $ 6,170 accounts receivable $ 9,000 accounts payable 8,500 accum. depr- building 13,525 supplies 1,590 accum. depr- equipment 6,340 prepaid insurance 345 net income 12,500 land 25,000 total current assets $ 42,105 total liabilities $ 40,865 stockholders equity property, plant, and equipment: wages payable $ 500 building $ 45,500 retained earnings 10,000 equipment 28,250 total stockholders' equity $ 64,490 total property, plant, and equipment 73,750 total assets $115,855 total liabilities and stockholders' equity $115,855 (a) list the errors in the balance sheet above and (b) prepare a corrected balance sheet using ms excel
Answers: 3
You know the right answer?
Southern Industries uses a job order costing. The following information was drawn from the Company’s...
Questions
Questions on the website: 13722367