Marle Construction enters into a contract with a customer to build a warehouse for $950,000 on March 30, 2018 with a performance bonus of $50,000 if the building is completed by July 31, 2018. The bonus is reduced by $10,000 each week that completion is delayed. Marle commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes:
Completed by Probability
July 31, 2018 65%
August 7, 2018 25%
August 14, 2018 5%
August 21, 2018 5%
Required:
1. The transaction price for this transaction, based on the expected value approach, is.
Select one:
a. $950,000
b. $995,000
o. $685,000
d. $652,500

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 15:30
Josie, an unmarried taxpayer, has $155,000 in salary, $10,000 in income from a passive investment in a limited partnership, and a $26,000 passive loss from a real estate rental activity in which she actively participates. if her modified adjusted gross income is $155,000, how much of the $26,000 loss is deductible
Answers: 1
question
Business, 22.06.2019 04:30
Georgia's gross pay was 35,600 this year she is to pay a federal income tax of 16% how much should georgia pay in federal income ax this year
Answers: 1
question
Business, 22.06.2019 06:00
When an interest-bearing note comes due and is uncollectible, the journal entry includes debitingaccounts receivable and crediting notes receivable and interest revenue.accounts receivable and crediting interest revenue.notes receivable and crediting accounts receivable and interest revenue.notes receivable and crediting accounts receivable.
Answers: 3
question
Business, 22.06.2019 11:00
Why are the four primary service outputs of spatial convenience, lot size, waiting time, and product variety important to logistics management? provide examples of competing firms that differ in the level of each service output provided to customers?
Answers: 1
You know the right answer?
Marle Construction enters into a contract with a customer to build a warehouse for $950,000 on March...
Questions
Questions on the website: 13722362