Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.

A)day 6
B)day 3
C)day 4

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 14:30
Processors can be or which is an indicator of how much data the processors can handle at a given point in time, with the processor being more powerful.
Answers: 2
question
Business, 22.06.2019 19:00
Tri fecta, a partnership, had revenues of $369,000 in its first year of operations. the partnership has not collected on $45,000 of its sales and still owes $39,500 on $155,000 of merchandise it purchased. there was no inventory on hand at the end of the year. the partnership paid $27,000 in salaries. the partners invested $48,000 in the business and $23,000 was borrowed on a five-year note. the partnership paid $2,070 in interest that was the amount owed for the year and paid $9,500 for a two-year insurance policy on the first day of business. compute net income for the first year for tri fecta.
Answers: 2
question
Business, 22.06.2019 20:10
Given the following information, calculate the savings ratio: liabilities = $25,000 liquid assets = $5,000 monthly credit payments = $800 monthly savings = $760 net worth = $75,000 current liabilities = $2,000 take-home pay = $2,300 gross income = $3,500 monthly expenses = $2,050 multiple choice 2.40% 3.06% 34.78% 33.79% 21.71%
Answers: 2
question
Business, 22.06.2019 20:20
Amanager of a store that sells and installs spas wants to prepare a forecast for january and june of next year. her forecasts are a combination of trend and seasonality. she uses the following equation to estimate the trend component of monthly demand: ft = 30+5t, where t = 1 in january of this year. seasonal relatives are 0.60 for january and 1.50 for june. what demands should she predict for january and june of next year
Answers: 2
You know the right answer?
Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its...
Questions
question
Mathematics, 01.04.2021 05:50
question
Biology, 01.04.2021 05:50
question
Mathematics, 01.04.2021 05:50
question
Chemistry, 01.04.2021 05:50
question
Mathematics, 01.04.2021 05:50
question
Mathematics, 01.04.2021 05:50
Questions on the website: 13722367