Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value. EV is the earned value, AC is the actual cost, and BAC is the budget at completion.
PV = $23,000
EV = $20,000
AC = $25,000
BAC = $120,000
a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
d. Use the schedule performance index (SPI) to estimate how long it will take to finish this project.
e. Sketch the earned value chart based on this project

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 23:00
You and your new australian bride matilda, are applying for a loan and are required to submit a balance sheet with your net worth. you own a 2008 toyota camry that you bought last month for $9,995. the kelly blue book value for this car is $13,995. you owe $8,150 on the car loan for the camry. you pay off your visa credit card every month and have not paid any credit card interest this year. the current visa credit card balance is $3,522, and the next statement is due in 15 days. you have a student loan balance of $6,500. you presently have $425 in your checking account and $1,540 in your savings account. you own 100 shares of ibm stock that you purchased for $85.50 per share. one share of ibm is now selling for $158.42. you own computers and other electronics that you purchased for $4,100 but could probably sell today on e-bay for $1,800. your gross income is $80,000 per year. what is your current net worth? (see wb ch. 2 example 2.3)
Answers: 1
question
Business, 22.06.2019 13:30
Hundreds of a bank's customers have called the customer service call center to complain that they are receiving text messages on their phone telling them to access a website and enter personal information to resolve an issue with their account. what action should the bank take?
Answers: 2
question
Business, 22.06.2019 14:50
Pear co.’s income statement for the year ended december 31, as prepared by pear’s controller, reported income before taxes of $125,000. the auditor questioned the following amounts that had been included in income before taxes: equity in earnings of cinn co. $ 40,000 dividends received from cinn 8,000 adjustments to profits of prior years for arithmetical errors in depreciation (35,000) pear owns 40% of cinn’s common stock, and no acquisition differentials are relevant. pear’s december 31 income statement should report income before taxes of
Answers: 3
question
Business, 22.06.2019 19:00
The market demand curve for a popular teen magazine is given by q = 80 - 10p where p is the magazine price in dollars per issue and q is the weekly magazine circulation in units of 10,000. if the circulation is 400,000 per week at the current price, what is the consumer surplus for a teen reader with maximum willingness to pay of $3 per issue?
Answers: 1
You know the right answer?
Given the following information for a one-year project, answer the following questions. Recall that...
Questions
question
Mathematics, 26.02.2020 05:59
question
Mathematics, 26.02.2020 05:59
question
Mathematics, 26.02.2020 05:59
question
Mathematics, 26.02.2020 05:59
Questions on the website: 13722363