The welding department supplies parts to the final assembly line. Management decides to implement a kanban system and has collected the following data.

a. The daily demand is 1,700 units.
b. The production lead time is 2 days (this includes processing time, transport time, and waiting time).
c. Management has decided to have 2 day(s) of safety stock
d. One container fits 350 units

How many kanban containers will be needed to support this system?

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 13:40
Aztic inc., a manufacturer of sports goods, plans to expand its operations to various other countries. during market research, it avoids countries where the dominant population is mostly rural. in this case, aztic inc. is assessing the of the countries
Answers: 1
question
Business, 22.06.2019 01:00
When color is used on a topographical drawing, black is used to represent what?
Answers: 1
question
Business, 22.06.2019 10:30
When sending a claim to an insurance company for services provided by the physician, why are both icd-10 and cpt codes required to be submitted? how are these codes dependent upon each other? what would be the result of not submitting both codes on a medical claim to an insurance company?
Answers: 2
question
Business, 22.06.2019 12:10
Lambert manufacturing has $100,000 to invest in either project a or project b. the following data are available on these projects (ignore income taxes.): project a project b cost of equipment needed now $100,000 $60,000 working capital investment needed now - $40,000 annual cash operating inflows $40,000 $35,000 salvage value of equipment in 6 years $10,000 - both projects will have a useful life of 6 years and the total cost approach to net present value analysis. at the end of 6 years, the working capital investment will be released for use elsewhere. lambert's required rate of return is 14%. the net present value of project b is:
Answers: 2
You know the right answer?
The welding department supplies parts to the final assembly line. Management decides to implement a...
Questions
question
History, 05.05.2021 20:50
question
Mathematics, 05.05.2021 20:50
question
Mathematics, 05.05.2021 20:50
Questions on the website: 13722361