A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here:
Immediate
Activity Designation Predecessor Time in Days
Break down both machines A None 3
Clean machine 1 B A 3
Clean machine 2 C A 3
Re-set machine 1 D B 4
Re-set machine 2 E C 2
Re-calibrate both machines F D and E 1
Final test G F 1
Using CPM, which activities have slack in this project?
a. A, B, C
b. B, D
c. Only C
d. C, E
e. F, G

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 02:30
Based on the supply and demand theory, why do medical doctors earn higher wages than child-care workers?
Answers: 1
question
Business, 22.06.2019 12:40
Kumar consulting operates several stock investment portfolios that are used by firms for investment of pension plan assets. last year, one portfolio had a realized return of 12.6 percent and a beta coefficient of 1.15. the average t-bond rate was 7 percent and the realized rate of return on the s& p 500 was 12 percent. what was the portfolio's alpha?
Answers: 1
question
Business, 22.06.2019 16:00
What is used by accountant to analyze transactions ?
Answers: 2
question
Business, 22.06.2019 16:40
Differentiate between the trait, behavioral, and results-based performance appraisal systems, providing an example where each would be most applicable.
Answers: 1
You know the right answer?
A company must perform a maintenance project consisting of seven activities. The activities, their p...
Questions
Questions on the website: 13722362