Consider two different machines A and B that could be used at a station. Machine A has a mean effective process time of 1.0 hours and an SCV of 0.25. Machine B has a mean effective process 푡푒푐2푒time of 0.85 hour and an SCV of 4.

a. For an arrival rate of 0.92 job per hour with ce^2 = 1, which machine will have a shorter average cycle time?

b. Now put two machines of type A at the station and double the arrival rate (i. e., double the capacity and the throughput). What happens to cycle time? Do the same for machine B. Which type of machine produces shorter average cycle time?

c. With only one machine at each station, let the arrival rate be 0.95 job per hour with ce^2= 1. Recompute the average time spent at the stations for both machine A and machine B. Compare with a.

d. Consider the station with one machine of type A.

i. Let the arrival rate be one-half. What is the average time spent at the station? What happens to the average time spent at the station if the arrival rate is increased by one percent (i. e., to 0.505)? What percentage increase in wait time does this represent?

ii. Let the arrival rate be 0.95. What is the average time spent at the station? What happens to the average time spent at the station if the arrival rate is increased by one percent (i. e., to 0.9595)? What percentage increase in wait time does this represent?

ansver
Answers: 2

Another question on Business

question
Business, 21.06.2019 20:30
Monetary policy in the united states is carried out primarily by which of the following agencies? a. the department of the treasury b. the small business association c. the federal reserve bank d. the u.s. mint 2b2t
Answers: 1
question
Business, 22.06.2019 15:30
Uknow what i love about i ask a dumb question it is immediately answered but when i ask a real question it take like an hour to get answered
Answers: 2
question
Business, 22.06.2019 16:00
Analyzing and computing accrued warranty liability and expense waymire company sells a motor that carries a 60-day unconditional warranty against product failure. from prior years' experience, waymire estimates that 2% of units sold each period will require repair at an average cost of $100 per unit. during the current period, waymire sold 69,000 units and repaired 1,000 units. (a) how much warranty expense must waymire report in its current period income statement? (b) what warranty liability related to current period sales will waymire report on its current period-end balance sheet? (hint: remember that some units were repaired in the current period.) (c) what analysis issues must we consider with respect to reported warranty liabilities?
Answers: 1
question
Business, 22.06.2019 21:30
The adjusted trial balance for china tea company at december 31, 2018, is presented below:
Answers: 1
You know the right answer?
Consider two different machines A and B that could be used at a station. Machine A has a mean effect...
Questions
question
Mathematics, 04.07.2019 12:00
question
Mathematics, 04.07.2019 12:00
question
Business, 04.07.2019 12:00
question
Mathematics, 04.07.2019 12:00
question
Mathematics, 04.07.2019 12:00
question
Geography, 04.07.2019 12:00
Questions on the website: 13722367