A master production schedule quantity of 300 units will arrive in week 6. Weekly demand over weeks 3 through 10 is forecasted at 50 units. At present, orders have been booked in various quantities in weeks 1, 2, 3, and 4. What is available to promise for week 6?
A) 50
B) 6
C) 300
D) 100
E) cannot be determined without projected on-hand information

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 23:30
As manager of kids skids, meghan wants to develop her relationship management skills. in order to do this, she learns how to
Answers: 2
question
Business, 22.06.2019 02:20
Neon light company of kansas city ships lamps and lighting appliances throughout the country. ms. neon has determined that through the establishment of local collection centers around the country, she can speed up the collection of payments by one and one-half days. furthermore, the cash management department of her bank has indicated to her that she can defer her payments on her accounts by one-half day without affecting suppliers. the bank has a remote disbursement center in florida. a. if neon light company has $2.90 million per day in collections and $1.18 million per day in disbursements, how many dollars will the cash management system free up?
Answers: 2
question
Business, 22.06.2019 08:30
Sonic corp. manufactures ski and snowboarding equipment. it has estimated that this year there will be substantial growth in its sales during the winter months. it approaches the bank for credit. what is the purpose of such credit known as? a. expansion b. inventory building c. debt management d. emergency maintenance
Answers: 3
question
Business, 22.06.2019 13:10
Laval produces lamps and home lighting fixtures. its most popular product is a brushed aluminum desk lamp. this lamp is made from components shaped in the fabricating department and assembled in the assembly department. information related to the 22,000 desk lamps produced annually follows.direct materials $280,000direct labor fabricating department (8,000 dlh × $24 per dlh) $192,000assembly department (16,600 dlh × $26 per dlh) $431,600machine hours fabricating department $15,200mhassembly department $20,850mhexpected overhead cost and related data for the two production departments follow.fabricating assemblydirect labor hours 150,000dlh 295,000dlhmachine hours 161,000mh 128,000mhoverhead cost $400,000 430,000required1. determine the plantwide overhead rate for laval using direct labor hours as a base.2. determine the total manufacturing cost per unit for the aluminum desk lamp using the plantwide overhead rate.3. compute departmental overhead rates based on machine hours in the fabricating department and direct labor hours in the assembly department.4. use departmental overhead rates from requirement 3 to determine the total manufacturing cost per unit for the aluminum desk lamps.
Answers: 3
You know the right answer?
A master production schedule quantity of 300 units will arrive in week 6. Weekly demand over weeks 3...
Questions
Questions on the website: 13722367