The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below. What is the overall risk factor for the project?

A) Less than or equal to 0.7

B) Greater than 0.7 but less than or equal to 0.8

C) Greater than 0.8 but less than or equal to 0.9

D) Greater than 0.9

Maturity 0.7 Cost 0.4

Complexity 0.6 Schedule 0.6

Dependency 0.8 Reliability 0.8

Performance 0.9

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 02:50
Acompany set up a petty cash fund with $800. the disbursements are as follows: office supplies $300 shipping $50 postage $30 delivery expense $350 to create the fund, which account should be credited? a. postage b. cash at bank c. supplies d. petty cash
Answers: 2
question
Business, 22.06.2019 12:50
Demand increases by less than supply increases. as a result, (a) equilibrium price will decline and equilibrium quantity will rise. (b) both equilibrium price and quantity will decline. (c) both equilibrium price and quantity will rise
Answers: 3
question
Business, 22.06.2019 20:30
When many scrum teams are working on the same product, should all of their increments be integrated every sprint?
Answers: 3
question
Business, 22.06.2019 21:30
The adjusted trial balance for china tea company at december 31, 2018, is presented below:
Answers: 1
You know the right answer?
The project team toiled long into the night to develop consequence of failure scores and probability...
Questions
question
Mathematics, 17.12.2020 21:40
question
Mathematics, 17.12.2020 21:40
question
Chemistry, 17.12.2020 21:40
question
Mathematics, 17.12.2020 21:40
question
Mathematics, 17.12.2020 21:40
Questions on the website: 13722367