Each of Boggart’s production managers (annual salary cost, $45,000) can oversee 60,000 machine hours of manufacturing activity. Thus, if the company has 50,000 hours of manufacturing activity, one manager is needed; for 75,000 hours, two managers are needed; for 125,000 hours, three managers are needed; and so forth. Boggart’s salary cost can best be described as a:

1.variable cost.
2.semivariable cost.
3.step-variable cost.
4.fixed cost.
5.step-fixed cost.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 05:10
Suppose that the free states of eldricia, a small nation, has consumption, investment, government purchases, imports, and exports as follows. consumption $140 investment $50 government purchases $45 imports $30 exports $15 calculate the free states of eldricia's gdp
Answers: 2
question
Business, 22.06.2019 20:30
You are in the market for a new refrigerator for your company’s lounge, and you have narrowed the search down to two models. the energy efficient model sells for $700 and will save you $45 at the end of each of the next five years in electricity costs. the standard model has features similar to the energy efficient model but provides no future saving in electricity costs. it is priced at only $500. assuming your opportunity cost of funds is 6 percent, which refrigerator should you purchase
Answers: 3
question
Business, 23.06.2019 03:50
What is inventory turnover? explain the effect of a high inventory turnover during the christmas shopping season.
Answers: 1
question
Business, 23.06.2019 10:00
Which statement was true in the past but is not generally true today? a. the training and education costs for some jobs will prohibit some people from entering that career be b. young people tend to go into the same job that their parents and grandparents did see c. people need a basic level of education before they meet requirements to professional schools d. people will probably have more than one job in their active working lives
Answers: 1
You know the right answer?
Each of Boggart’s production managers (annual salary cost, $45,000) can oversee 60,000 machine hours...
Questions
question
Mathematics, 31.10.2020 08:10
question
English, 31.10.2020 08:10
question
Mathematics, 31.10.2020 08:10
question
Computers and Technology, 31.10.2020 08:10
Questions on the website: 13722362