The following schedule was prepared by the production manager of Marymount Metal Shop:

CUTTING POLISHING
Job Start Finish Start Finish
A 0 2 2 5
B 2 6 6 9
C 6 11 11 13
D 11 15 15 20
E 15 17 20 23
F 17 20 23 24
G 20 21 24 28

Determine a schedule that will result in earliest completion of all jobs on this list.

ansver
Answers: 1

Another question on Business

question
Business, 21.06.2019 14:00
Alex is a working professional and has managed to save a small amount of money from his earnings. he wants to invest in something that is customized to his risk appetite. which financial institution should he choose? a. hedge funds b. mutual funds c. life insurance companies d. credit unions e. pension funds
Answers: 1
question
Business, 21.06.2019 21:00
In order to minimize project risk which step comes after the step of identifying risks
Answers: 1
question
Business, 22.06.2019 02:00
Greater concern for innovation and quality has shifted the job trend to using more broadly defined jobs. t/f
Answers: 1
question
Business, 22.06.2019 09:00
Brian has been working for a few years now and has saved a substantial amount of money. he now wants to invest 50 percent of his savings in a bank account where it will be locked for three years and gain interest. which type of bank account should brian open? a. savings account b. money market account c. checking account d. certificate of deposit
Answers: 1
You know the right answer?
The following schedule was prepared by the production manager of Marymount Metal Shop:

...
Questions
question
Mathematics, 06.05.2020 21:04
question
Physics, 06.05.2020 21:04
Questions on the website: 13722359