Your next project consists of 8 consecutive 8-day activities, each estimated by a different worker in your organization. Your organizational culture dictates that you add your own safety margin of 3 days into your estimates. Unbeknownst to you, the project manager has recently converted to a critical chain project management view. The project manager knows perfectly well what sorts of games are played with activity estimates and she knows exactly how much activity padding takes place. What will the overall project safety margin be once the project manager reviews your estimates and makes the project schedule

ansver
Answers: 3

Another question on Business

question
Business, 21.06.2019 17:20
Which of the following is a disadvantage of equity alliances when compared to non-equity alliances? 1. they are reflective of weaker ties between firms.2. they do not permit the exchange of explicit knowledge.3. they are more likely to bring about lack of trust and commitment.4. they require significantly higher levels of investment.
Answers: 2
question
Business, 21.06.2019 22:10
3. now assume that carnival booked lady antebellum in december 2016 to perform on the june 2017 western caribbean cruise. further assume that carnival pays lady antebellum its entire performance fee of $52,000 on december 28, 2016, for the june 2017 cruise. what journal entry will carnival make on december 28, 2016, for its payment to lady antebellum?
Answers: 1
question
Business, 22.06.2019 16:10
Omnidata uses the annualized income method to determine its quarterly federal income tax payments. it had $100,000, $50,000, and $90,000 of taxable income for the first, second, and third quarters, respectively ($240,000 in total through the first three quarters). what is omnidata's annual estimated taxable income for purposes of calculating the third quarter estimated payment?
Answers: 1
question
Business, 22.06.2019 16:30
Why are there so many types of diversion programs for juveniles
Answers: 2
You know the right answer?
Your next project consists of 8 consecutive 8-day activities, each estimated by a different worker i...
Questions
question
Geography, 11.11.2019 22:31
question
Computers and Technology, 11.11.2019 22:31
question
Mathematics, 11.11.2019 22:31
question
Health, 11.11.2019 22:31
Questions on the website: 13722360