Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $33 million of costs and estimates an additional $88 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $57 million and estimated an additional $38 million in costs to complete the project.
Indiana:
A. Recognized no gross profit or loss on the project in 2021.
B. Recognized $81.00 million loss on the project in 2021.
C. Recognized $38.00 million loss on the project in 2021.
D. Recognized $13.50 million gross profit on the project in 2021.

ansver
Answers: 2

Another question on Business

question
Business, 22.06.2019 09:40
Wilson center is a private not-for-profit voluntary health and welfare entity. during 2017, it received unrestricted pledges of $638,000, 65 percent of which were payable in 2017, with the remainder payable in 2018 (for use in 2018). officials estimate that 14 percent of all pledges will be uncollectible. a. how much should wilson center report as contribution revenue for 2017? b. in addition, a local social worker, earning $20 per hour working for the state government, contributed 600 hours of time to wilson center at no charge. without these donated services, the organization would have hired an additional staff person. how should wilson center record the contributed service?
Answers: 2
question
Business, 22.06.2019 20:20
Direct materials (4.2 x $15) $ 63direct labor ($12 x 17.5) $210manufacturing overhead ($2.40 x 17.5) $42total job cost $ 315dougan, inc. allocates overhead based on a predetermined overhead rate of $2.40 per direct labor hour. employees are paid $12.00 per hour. job 24 requires 4.2 pounds of direct materials at a cost of $15.00 per pound. employees worked a total of 17.5 hours to complete the job. actual manufacturing overhead costs totaled $80,000 for the year for the company. how much is the cost of job 24?
Answers: 1
question
Business, 22.06.2019 22:20
David consumes two things: gasoline (q 1) and bread (q 2). david's utility function is u(q 1, q 2)equals70q 1 superscript 0.5 baseline q 2 superscript 0.5. let the price of gasoline be p 1, the price of bread be p 2, and income be y. derive david's demand curve for gasoline. david's demand for gasoline is q 1equals nothing. (properly format your expression using the tools in the palette. hover over tools to see keyboard shortcuts. e.g., a subscript can be created with the _ character.)
Answers: 1
question
Business, 23.06.2019 00:50
Aproduction department's output for the most recent month consisted of 8,000 units completed and transferred to the next stage of production and 5,000 units in ending work in process inventory. the units in ending work in process inventory were 50% complete with respect to both direct materials and conversion costs. calculate the equivalent units of production for the month, assuming the company uses the weighted average method.
Answers: 3
You know the right answer?
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be receive...
Questions
question
Mathematics, 10.12.2019 16:31
question
Spanish, 10.12.2019 16:31
question
Mathematics, 10.12.2019 16:31
question
Spanish, 10.12.2019 16:31
Questions on the website: 13722362