Drum buffers are:

A) A safety margin separating different projects scheduled to use the same resource.
B) Extra safety that is applied to a project immediately after the use of the constrained resource.
C) A constraint separating different projects that requires a common buffer.
D) Extra safety that is applied to a project immediately before the use of the constrained resource.

ansver
Answers: 1

Another question on Business

question
Business, 22.06.2019 11:40
In each of the following, what happens to the unemployment rate? does the unemployment rate give an accurate impression of what’s happening in the labor market? a.esther lost her job and begins looking for a new one.b.sam, a steelworker who has been out of work since his mill closed last year, becomes discouraged and gives up looking for work.c.dan, the sole earner in his family of 5, just lost his $90,000 job as a research scientist. immediately, he takes a part-time job at starbucks until he can find another job in his field.
Answers: 2
question
Business, 22.06.2019 12:30
land, a building and equipment are acquired for a lump sum of $ 1,000,000. the market values of the land, building and equipment are $ 300,000, $ 800,000 and $ 300,000, respectively. what is the cost assigned to the equipment? (do not round any intermediary calculations, and round your final answer to the nearest dollar.)
Answers: 1
question
Business, 22.06.2019 16:30
Suppose that electricity producers create a negative externality equal to $5 per unit. further suppose that the government imposes a $5 per-unit tax on the producers. what is the relationship between the after-tax equilibrium quantity and the socially optimal quantity of electricity to be produced?
Answers: 2
question
Business, 22.06.2019 17:50
On january 1, eastern college received $1,350,000 from its students for the spring semester that it recorded in unearned tuition and fees. the term spans four months beginning on january 2 and the college spreads the revenue evenly over the months of the term. assuming the college prepares adjustments monthly, what amount of tuition revenue should the college recognize on february 28?
Answers: 2
You know the right answer?
Drum buffers are:

A) A safety margin separating different projects scheduled to use the...
Questions
question
Mathematics, 06.07.2020 21:01
question
Mathematics, 06.07.2020 21:01
question
Chemistry, 06.07.2020 21:01
Questions on the website: 13722362